Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Port cells | All 46 doors in place

    In ITER, ordinary objects and features often take on an awesome dimension. Take the doors that seal off the port cells around the Tokamak for instance. Doors th [...]

    Read more

  • Toroidal field coils | Two make a pair

    One of the essential 'building blocks' of the ITER Tokamak is the pre-assembly of two toroidal field coils, one vacuum vessel sector and corresponding panels of [...]

    Read more

  • Industrial milestone | Cryostat manufacturing comes to an end in India

    With a flag-off ceremony on 30 June, India's L&T Heavy Engineering marked the end of an eight-year industrial adventure—the manufacturing of the ITER cryost [...]

    Read more

  • Local partners | A celebration for ITER's "vital artery"

    ITER is made possible through the work of thousands of scientists, engineers, workers of all trades and industries across the globe. It is also made possible by [...]

    Read more

  • Photo reportage | Travelling with a coil

    From the salt marshes of the inland sea Étang-de-Berre to the rolling hills around the ITER site (with a view of some of the highest alpine summits) an ITER con [...]

    Read more

Of Interest

See archived entries

Coil winding facility

Gantry crane passes load tests

However complex the science or sophisticated the technology at ITER, there is one simple activity that conditions future success—the ability to lift and manoeuvre exceptionally heavy loads during the project assembly phase.

A 540-tonne load, representing 125 percent of the crane's nominal lifting capacity, is attached to the beams for static tests. Dynamic operations followed at 110 percent in order to monitor the deformation of the beams. (Click to view larger version...)
A 540-tonne load, representing 125 percent of the crane's nominal lifting capacity, is attached to the beams for static tests. Dynamic operations followed at 110 percent in order to monitor the deformation of the beams.
With a nominal lifting capacity of 1,500 tonnes, the undisputed champion of ITER weightlifters is the double overhead crane in the Assembly Hall. Second on the podium is the gantry crane in the Poloidal Field Coils Winding Facility—a 30-metre-in-diameter steel structure supported by four hydraulic towers traveling on rails, capable of lifting the heaviest components of the ring-shaped coils throughout the last stages of fabrication.

Personnel from the European Domestic Agency and from crane manufacturer Ale Heavy Lift are overseeing the load tests. Europe is responsible for procuring 5 out of the 6 poloidal field coils required for ITER operation. (Click to view larger version...)
Personnel from the European Domestic Agency and from crane manufacturer Ale Heavy Lift are overseeing the load tests. Europe is responsible for procuring 5 out of the 6 poloidal field coils required for ITER operation.
Load tests for the gantry crane began on 16 February with static operations at 125 percent of its nominal lifting capacity of 400 tonnes. Dynamic operations followed at 110 percent in order to monitor the deformation of the beams. With a deflection of less than 119 millimetres, the tests were conclusive.

The bright red gantry crane was tested in three operational lifting configurations corresponding to poloidal field coils #2 and #5 (up to 342 tonnes, Ø 17 metres), poloidal field coils #3 and #4 (up to 385 tonnes, Ø 24 metres), and finally poloidal field coil #6 (396 tonnes, Ø 8.5 metres)¹.

¹ Poloidal field coil #6 (PF6) is being manufactured in China under a European contract but will be cold tested in the on-site poloidal field coil facility.
 
For more on the poloidal field coils click here and here.


return to the latest published articles