  • Port cells | All 46 doors in place

    In ITER, ordinary objects and features often take on an awesome dimension. Take the doors that seal off the port cells around the Tokamak for instance. Doors th [...]

    Read more

  • Toroidal field coils | Two make a pair

    One of the essential 'building blocks' of the ITER Tokamak is the pre-assembly of two toroidal field coils, one vacuum vessel sector and corresponding panels of [...]

    Read more

  • Industrial milestone | Cryostat manufacturing comes to an end in India

    With a flag-off ceremony on 30 June, India's L&T Heavy Engineering marked the end of an eight-year industrial adventure—the manufacturing of the ITER cryost [...]

    Read more

  • Local partners | A celebration for ITER's "vital artery"

    ITER is made possible through the work of thousands of scientists, engineers, workers of all trades and industries across the globe. It is also made possible by [...]

    Read more

  • Photo reportage | Travelling with a coil

    From the salt marshes of the inland sea Étang-de-Berre to the rolling hills around the ITER site (with a view of some of the highest alpine summits) an ITER con [...]

    Read more

Of Interest

See archived entries

ITER assembly

First large tool rises

ITER's first 22-metre-tall vacuum vessel sector sub-assembly tool is going up quickly in the Assembly Hall.

 (Click to view larger version...)
After a long period during which the anchoring elements—including base plates and rails—were set into place and precise measurements taken, the installation of ITER's first giant assembly tool is underway.

The inboard column already stands at 18 metres, with only 4 metres to go to reach its full height. To either side of the column, lateral wings are under construction and two other tall columns—the outboard columns—will be erected in the days and weeks to come. A testing phase will follow.

The tool, once fully erected, will be capable of supporting loads of 1,200 tonnes. Vacuum vessel sectors shipped from Europe and Korea will first be upended from their horizontal shipping position, and then suspended vertically by one of two sector sub-assembly tools while a pair of toroidal field coils plus thermal shielding is attached. The final assembly will be transported by overhead crane to the Tokamak assembly arena.

 (Click to view larger version...)

In all, about half of the major components for the first tool have been installed. In parallel, the elements for the second tool have been manufactured and assembled at Taekyung Heavy Industries (THI) in Korea, where testing is underway.