Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Divertor | Far more than a fancy ashtray

    It has been likened to the filter of a swimming pool or an oversized ashtray. It has been called alien in shape and hellish in its affinity for heat. But whatev [...]

    Read more

  • Council milestone #50 | The way to assembly is open

    Passing an ITER Council milestone is always an achievement. Passing this milestone at this moment is much more than that: it is a demonstration that, despite th [...]

    Read more

  • Deliveries | A third magnet ready for transport to ITER

    Three ITER magnets are now in transit to ITER from different points on the globe—two toroidal field magnets and one poloidal field coil. In terms of component w [...]

    Read more

  • Heaviest load yet | Europe's coil soon to hit the road

    It's big, it's heavy, it's precious and it's highly symbolic: the toroidal field coil that was unloaded at Marseille industrial harbour on 17 March is the most [...]

    Read more

  • Russia's ring coil | Entering the final sequence

    The smallest of ITER's poloidal field coils is entering the final sequence in a long series of activities that transform cable-in-conduit superconductor into a [...]

    Read more

Of Interest

See archived entries

ITER assembly

First large tool rises

ITER's first 22-metre-tall vacuum vessel sector sub-assembly tool is going up quickly in the Assembly Hall.

 (Click to view larger version...)
After a long period during which the anchoring elements—including base plates and rails—were set into place and precise measurements taken, the installation of ITER's first giant assembly tool is underway.

The inboard column already stands at 18 metres, with only 4 metres to go to reach its full height. To either side of the column, lateral wings are under construction and two other tall columns—the outboard columns—will be erected in the days and weeks to come. A testing phase will follow.

The tool, once fully erected, will be capable of supporting loads of 1,200 tonnes. Vacuum vessel sectors shipped from Europe and Korea will first be upended from their horizontal shipping position, and then suspended vertically by one of two sector sub-assembly tools while a pair of toroidal field coils plus thermal shielding is attached. The final assembly will be transported by overhead crane to the Tokamak assembly arena.

 (Click to view larger version...)

In all, about half of the major components for the first tool have been installed. In parallel, the elements for the second tool have been manufactured and assembled at Taekyung Heavy Industries (THI) in Korea, where testing is underway.