Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Image of the week | Tokamak-sur-mer

    At the height of the heat wave, in late June, surface temperature on the ITER worksite climbed to the 50 °C range. To continue work—and protect workers—a series [...]

    Read more

  • Space propulsion | Have fusion, will travel

    The idea of propelling rockets and spaceships using the power of the atom is nothing new: the Manhattan Project in the mid-1940s as well as countless endeavours [...]

    Read more

  • Cold fusion | End of story?

    Thirty years ago, two electrochemists at the University of Utah, Martin Fleischmann and Stanley Pons, created a sensation when they claimed they had achieved fu [...]

    Read more

  • Magnet feeders | Wave of deliveries ahead

    Several batches of magnet feeder components will arrive from China in September containing elements that need to be received, inspected and readied for installa [...]

    Read more

  • Tokamak cooling system procurement | Global team for better efficiency

    A unique work-sharing arrangement is expediting the design and fabrication of ITER's tokamak cooling water system and building the knowledge base that will be c [...]

    Read more

Of Interest

See archived entries

Images of the week

Three years of progress

Three years ago in late March, the most imposing features on the ITER platform were the workshops for the cryostat (left) and the poloidal field coils (right)—vast facilities where the manufacturing and/or assembly of some of ITER's largest components was set to begin.

 (Click to view larger version...)
Construction of the Assembly Hall had just begun, and the first steel pillars had been installed on opposite sides of the building's concrete floor slab. In the 90 x 130 metre area reserved for the Tokamak Complex, nothing yet had emerged above the platform level—work was concentrated at the level of the B2 slab, where preparatory works were underway for the construction of the bioshield.

 (Click to view larger version...)
Three years later the difference is striking. In this picture taken last week from the same angle, the 60-metre-tall Assembly Hall and its poster of the ITER Tokamak are a towering presence that completely hides the Cryostat Workshop from view. To the right, the Poloidal Field Coils Winding Facility is masked by a cluster of plant buildings.

And in the area of the Tokamak Complex, some of the walls now stand four storeys above platform level and the massive 30-metre-tall bioshield has been finalized.

However impressive the photo comparison may be, a large part of the progress that ITER has achieved since 2015 cannot be detected in these snapshots. Hundreds of components, both large and small, have been manufactured and safely delivered to the construction site. Many more—among them some of the largest and most challenging ITER components—are in various stages of advanced fabrication or factory acceptance testing.

According to the stringent metrics that monitor project performance ITER has now completed 53.7% of the total work scope on the road to First Plasma (calculated on the base of all design, construction, manufacturing, delivery, assembly, installation, and commissioning activities).


return to the latest published articles