Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

  • Visit | US Energy Secretary Rick Perry gets first-hand look at ITER

    Marking an important step in the US review of ITER Project progress, on Wednesday 11 July ITER Organization received a visit from the Head of the United States [...]

    Read more

Of Interest

See archived entries

Poloidal field coils

Turning tables and hot resin

One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, impregnation and assembly activities for ITER's largest ring-shaped magnets. Manufacturing is underway now on a 17-metre-in-diameter poloidal field coil called PF5.

 (Click to view larger version...)
In the first step of the process, the raw material—niobium-titanium conductor—is wound into a flat, double-layer, spiralled coil called a double pancake. Several layers of glass-fibre tape are applied as the conductor enters the winding table to insulate the conductor turns from one another. In this photo, European contractors are winding the sixth in the series of eight double pancakes required by PF5. The winding table rotates slowly as conductor is fed simultaneously from two spools in a process known as "two-in-hand" winding.

 (Click to view larger version...)
After completing the winding, the next step is to shape the "terminations"—the areas that connect one conductor length electrically to another, or one double pancake to another. A portion of conductor is opened, the turn insulation is removed and moulds are brought close to the double pancake to shape its end into a "termination joggle."

 (Click to view larger version...)
The creation of a termination box comes next. The box is welded to the jacket of conductor on one end with a stainless steel pipe for liquid helium cooling exiting on the other end.

 (Click to view larger version...)
The double pancakes are then transported by overhead crane to the vacuum pressure impregnation station and lowered into a custom-fit mould. Epoxy resin, injected over the course of several hours, fills all gaps and hardens the glass-fibre tape under the effect of heat and pressure. A 36-hour "curing" phase at 140 °C completes the process, which gives the double pancake rigidity and ensures electrical insulation. During this process the conductor ends, which carry the terminations to be used for joints between the double pancakes, are isolated by an "insulation breaker," which keeps the resin from binding these areas. In this picture, one double pancake is undergoing impregnation in the background, while assembly is underway on the impregnation mould for another.

 (Click to view larger version...)
The final step is cold testing. Once the eight double pancakes for PF5 are stacked and assembled to form the complete winding pack, a second vacuum impregnation is performed to harden the entire assembly. The manufacturing process then ends with cold testing, during which the completed coil is cooled to low temperature (approximately 80 K) in order to simulate the thermal stresses and the work conditions that will be experienced during operation. In this way, the performance of the coils will be tested before their installation in the ITER machine.


return to the latest published articles