Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Tokamak Complex | A changing landscape

    For the past three years, the view from the top of the highest worksite crane has not changed much. Inside of the Tokamak Complex, 80 metres below, concrete gal [...]

    Read more

  • Ion cyclotron heating | How to pump 20 MW of power into 1 gram of plasma

    To power the ion cyclotron system, the ITER Organization and its partners are designing not only new antennas, which will be housed in the tokamak vessel, but a [...]

    Read more

  • 10 years ago in Newsline | White, silent and immobile

    Ten years ago, in mid-January 2010, heavy snow fell on Provence and the white blanket that settled on the ITER platform accentuated its main feature: utter empt [...]

    Read more

Of Interest

See archived entries

Breaking news

First component installed next week

In the third week of November, the ITER Organization will be installing the first component of the machine in the basement of the Tokamak Building.

Feeders are the lifeline of the ITER magnet system, relaying electrical power, cryogens, and instrumentation from outside of the cryostat into the powerful coils. This feeder segment will be the first machine component installed in the Tokamak pit. (Click to view larger version...)
Feeders are the lifeline of the ITER magnet system, relaying electrical power, cryogens, and instrumentation from outside of the cryostat into the powerful coils. This feeder segment will be the first machine component installed in the Tokamak pit.
The 10-metre, 6-tonne metal component is one segment of the magnet feeder that will relay electrical power, cryogenic fluids and instrumentation cables from outside of the machine in to poloidal field coil #4. The specific section to be installed, called a "feedthrough," will cross through the bioshield and cryostat at the lowest (B2) level of the building.

Delivered by the Chinese Domestic Agency to ITER last year, the component has undergone testing at the MIFI workshop (Magnet Infrastructure Facilities for ITER), which is operated jointly by a team from ITER and the French Alternative Energies and Atomic Energy Commission (CEA).

Most recently, the lifting operation was tested at MIFI using a specially designed tool delivered by the Korean Domestic Agency (picture). Next week the component will be transferred by truck to a staging area, and then lifted up into the circular assembly area and lowered down 30 metres to the floor.

Stay tuned for a report in the 26 November issue of the ITER Newsline on the first act of the machine installation phase.


return to the latest published articles