Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Crane operator | A cabin in the sky

    There are times, at dusk, when the ITER construction platform resembles an airport, with roads and buildings illuminated by yellow and white lights. From their [...]

    Read more

  • Assembly | A colossal task made manageable

    For the execution of work during the next project phase—machine and plant assembly up to First Plasma—the ITER Organization has chosen a contractual approach th [...]

    Read more

  • Neutral Beam Test Facility | A new agreement for a new era

    The ITER Organization and the Italian consortium Consorzio RFX* have signed a new agreement governing the construction and operation of the ITER Neutral Beam Te [...]

    Read more

  • Load tests | Heavyweight champion

    The Assembly Hall, with its two giant tools towering 20 metres above ground, is one of the most spectacular locations on the ITER site. When a dummy load weighi [...]

    Read more

  • Fusion's new pioneers | How to go fast enough to make a difference

    Last month in New York, the Stellar Energy Foundation and the Fusion Industry Association co-hosted an invitation-only workshop: 'Roadmap to the Fusion Energy E [...]

    Read more

Of Interest

See archived entries

Breaking news

First component installed next week

In the third week of November, the ITER Organization will be installing the first component of the machine in the basement of the Tokamak Building.

Feeders are the lifeline of the ITER magnet system, relaying electrical power, cryogens, and instrumentation from outside of the cryostat into the powerful coils. This feeder segment will be the first machine component installed in the Tokamak pit. (Click to view larger version...)
Feeders are the lifeline of the ITER magnet system, relaying electrical power, cryogens, and instrumentation from outside of the cryostat into the powerful coils. This feeder segment will be the first machine component installed in the Tokamak pit.
The 10-metre, 6-tonne metal component is one segment of the magnet feeder that will relay electrical power, cryogenic fluids and instrumentation cables from outside of the machine in to poloidal field coil #4. The specific section to be installed, called a "feedthrough," will cross through the bioshield and cryostat at the lowest (B2) level of the building.

Delivered by the Chinese Domestic Agency to ITER last year, the component has undergone testing at the MIFI workshop (Magnet Infrastructure Facilities for ITER), which is operated jointly by a team from ITER and the French Alternative Energies and Atomic Energy Commission (CEA).

Most recently, the lifting operation was tested at MIFI using a specially designed tool delivered by the Korean Domestic Agency (picture). Next week the component will be transferred by truck to a staging area, and then lifted up into the circular assembly area and lowered down 30 metres to the floor.

Stay tuned for a report in the 26 November issue of the ITER Newsline on the first act of the machine installation phase.


return to the latest published articles