Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum vessel | Sector #6 is leak tight

    The first ITER vacuum vessel sector has passed a helium leak test on site with flying colours. Back in March 2020, as experts from the Korean Domestic Agency [...]

    Read more

  • Vacuum vessel | India completes in-wall shielding package

    The Indian Domestic Agency has completed the procurement of about 9,000 in-wall shielding blocks and accompanying support ribs, brackets and fasteners. The majo [...]

    Read more

  • Image of the week | Feeders for the coils

    One by one, whether large or small, the elements of the system that delivers electrical power, cryogenic fluids and instrumentation to the ITER magnets are arri [...]

    Read more

  • Busbar installation | "Power cords" thicker than train rails

    Connecting an electrical device to a power source requires an extension cord, generally made of stranded copper wire. Depending on the required current intensit [...]

    Read more

  • Manufacturing | The next sector in line

    Thanks to the experience acquired during the fabrication of the first production unit of the vacuum vessel, the Korean Domestic Agency and contractor Hyundai He [...]

    Read more

Of Interest

See archived entries

Electrical network

Independance Day

Ken Blackler, Deputy Head for Operations

For over 10 years, power has been supplied to ITER by the neighbouring CEA research facility. Since Saturday, however, the entire ITER site is independently powered from an electrical substation that draws power directly from the four hundred thousand volt (400 kV) national electrical grid. This power is needed initially to support ongoing construction activities.

Members of the electrical engineering and science/operations groups at ITER have a reason to smile: the first ITER system has successfully entered operation. (Click to view larger version...)
Members of the electrical engineering and science/operations groups at ITER have a reason to smile: the first ITER system has successfully entered operation.
After several months of tests and commissioning, the first ITER system—electrical distribution—has entered into operation. 

Four large transformers supplied by the US Domestic Agency step down the voltage to twenty two thousand volts (22 kV), which is then switched through a set of busbars into cables that distribute it around the site to transformers supplying each building.

The switching equipment was supplied by the US Domestic Agency and installed by the European Domestic Agency. By combining different in-kind contributions, along with the central control system developed by the ITER Organization itself, the electrical distribution system demonstrates the integration that will be continued now for each system to come.

Making such a switchover is not a simple process. It required the entire ITER site to be "turned off" so that the high voltage connections could be reconfigured. All construction work was halted, computer servers switched over onto their back-up generators, worksite offices closed, and silence settled onto the construction site for the first time in years as ventilators, pumps and machines slowed to a stop.

In a temporary control room on the platform, engineers worked during Saturday's shutdown to reconfigure the high voltage connections. Outside, the worksite was exceptionnally quiet ... (Click to view larger version...)
In a temporary control room on the platform, engineers worked during Saturday's shutdown to reconfigure the high voltage connections. Outside, the worksite was exceptionnally quiet ...
Meanwhile in a temporary control room setup in the Substation Building engineers worked on reconfiguring the networks, while teams of operators drove around the site switching off each building one at a time. At the end, the only building left with lights on was the substation itself, which supplies its own power. After the main incoming switches were swapped over, the buildings were switched back on one by one. Engineers watched carefully as the electrical load rose on each circuit, checking that the protection settings were correctly made and that the equipment worked as expected.

Before nightfall all the buildings were back to normal and the generators could be switched off. The next step was to wait for the start-of-work Monday. As building heating systems turned on and activity began, the loads increased and the new system settled down without a hitch.

The first ITER system has thus entered operation—the first of many such steps as we complete construction, take each system into operation, and build up to integrated commissioning, which will mark the official start of the ITER operations phase. Integrated commissioning will conclude with the machine's First Plasma.


return to the latest published articles