Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryoplant | First steps toward commissioning

    Every week since the beginning of November, a tube trailer filled with approximately 4,600 cubic metres (750 kg) of compressed gaseous helium delivers its load [...]

    Read more

  • Training | Seeking the next group of Monaco-ITER Fellows

    Recruitment opens for the next Monaco-ITER Postdoctoral Fellowship campaign on 17 January 2022. If your PhD was awarded after 1 January 2019—or you are about to [...]

    Read more

  • Contemporary art | Venet's "arcs" are as heavy as ITER coils

    A 'conceptual artist' among the most prominent on the art scene today, Bernar Venet is not impressed by massive towering steel structures like those in the ITER [...]

    Read more

  • Image of the week | Final activities on Europe's first sector

    The first vacuum vessel sector produced in Europe will arrive at ITER next year. Five of ITER's nine vacuum vessel sectors are the responsibility of Europe's AM [...]

    Read more

  • Vacuum vessel sector preparation | Lessons learned reduce work time by half

    In life as in the assembly of the ITER machine, 'lessons learned' are what makes progress possible. Gains in wisdom, time, skill, investment can be incremental; [...]

    Read more

Of Interest

See archived entries

Image of the week

Almost there

The Tokamak Building has reached its maximum height ... in terms of concrete that is. The "jewel box" in reinforced concrete will grow no more; instead, it will be brought to the level of the adjacent Assembly Hall by the addition of steel-structure walls and a roof.

The Tokamak Building requires two types of construction: concrete below (nearly completed) and steel above (installation beginning summer 2019). (Click to view larger version...)
The Tokamak Building requires two types of construction: concrete below (nearly completed) and steel above (installation beginning summer 2019).
The concrete portion of the building below will enclose the ITER machine. The airy gallery above—the Crane Hall—will provide the workspace needed as the heavy-lift assembly cranes travel back and forth between the buildings to deliver components into the Tokamak Pit.

On the south side of the Tokamak Building, visible in this picture, a concrete slab will be poured to "close off" the part of the structure that extends out wider than the Assembly Hall. (A similar slab will be poured on the opposite side.)

On top of the slabs, heavy structural pieces called "corbels" will support the steel pillars for the Crane Hall. The steel structure (pillars, walls, roof) is in production now and assembly operations are set to begin during the summer.



return to the latest published articles