Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Worksite postcards | Under fog and autumn light

    Due to its proximity to the Durance River and to the narrow gully spanned by the Bridge of Mirabeau, the area around ITER often experiences a peculiar meteorolo [...]

    Read more

  • Assembly Hall | Another massive paint job

    By the end of December, the massive painting job in the Assembly Hall will be complete and the building's floor will be as white and pristine as the landscape i [...]

    Read more

  • ITER India | Testing a neutral beam for diagnostics

    Every 23 seconds during fusion operation, a probe beam will penetrate deep into the core of the ITER plasma to aid in the detection of helium ash—one of fusion' [...]

    Read more

  • Welded attachments | Follow the laser projections

    How do you position 150,000 welded attachments on to a vacuum vessel the size of a house, each one needing to be accurately placed to less than a 4 mm target? [...]

    Read more

  • Visit | Our neighbour the Nobel

    In 2018, the Nobel Prize in Physics was awarded to Gérard Mourou for his work on ultra-short, extremely high-intensity laser pulses—the so-called 'chirped pulse [...]

    Read more

Of Interest

See archived entries

Europe

Fabrication begins on unique composite rings

After lengthy development, prototyping and test phases, the composite rings designed to help ITER's toroidal field coils cope with huge out-of-plane forces have been cleared for fabrication.

European contractor CNIM has designed the manufacturing process and tooling for winding, bonding, curing, dry machining, and inspecting the pre-compression rings. The first production unit is underway. © CNIM (Click to view larger version...)
European contractor CNIM has designed the manufacturing process and tooling for winding, bonding, curing, dry machining, and inspecting the pre-compression rings. The first production unit is underway. © CNIM
In ITER, the electromagnetic interaction between the toroidal field coil current and the magnetic field generated by the poloidal field coils will create huge stresses on the toroidal field coils. Pre-compression rings will be installed at the top and bottom of the coil structures to "push back" with a centripetal force of thousands of tonnes, suppressing any deflection and greatly reducing cyclic fatigue stresses.

ITER's pre-compression rings are among the largest and most highly stressed composite structures to be designed for a cryogenic environment. Five metres in diameter, with a cross-section of 33.7 cm x 28.8 cm, the rings are made of a composite that consists of more than one billion minuscule glass fibres glued together using epoxy resin.

Prototypes produced by European Domestic Agency contractor CNIM (Toulon, France) have responded well to the demanding tests underway since January, opening the way for fabrication to start on the first production unit. CNIM will manufacture nine pre-compression rings in all (three top, three bottom and three spare).

Dimensional measurements are performed before final machining. The five-metre-in-diameter, three-tonne components will be installed in sets of three at the top and bottom of the toroidal field coil structures to ''push back'' against deflection. (Three other rings will be manufactured as spares.) © CNIM (Click to view larger version...)
Dimensional measurements are performed before final machining. The five-metre-in-diameter, three-tonne components will be installed in sets of three at the top and bottom of the toroidal field coil structures to ''push back'' against deflection. (Three other rings will be manufactured as spares.) © CNIM
CNIM has partnered with Exel Composites (Finland) for the raw material—a pultruded laminate delivered in lengths of 2.8 km (2 mm thick) on spools. Each laminate profile is wound into one ring on specialized winding tooling, with alternate layers of 0.12 mm-thick epoxy tape applied. The completed ring is cured and then machined to the required final dimensions.

Winding started in late February and the first curing operations took place in March. All nine pre-compression rings are expected to be completed by mid-2020.

See the full report on the European Domestic Agency website.


return to the latest published articles