Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Sub-assembly tools

A Titan's big hug

A Titan's hug is a slow affair. For the sector sub-assembly tools, rotating both arms from "full open" to "full close" will require no less than four hours of near-imperceptible motion.

Resting on the ground to the left in this image, are the two 350-tonne mock loads that represent toroidal field coils. Tool load tests will begin in mid-July and last for about a month. (Click to view larger version...)
Resting on the ground to the left in this image, are the two 350-tonne mock loads that represent toroidal field coils. Tool load tests will begin in mid-July and last for about a month.
In the Assembly Hall everything is being readied for the tool load tests, which are scheduled to begin in mid-July and last for about one month.

Two 350-tonne test loads, each representing an ITER toroidal field coil, have been assembled on the floor at the entrance. Made of seven different steel-and-concrete modules, the dummies slightly exceed the weight of the actual coils but closely reproduce their centre of gravity and distribution of mass.

During the tests, the mock toroidal field loads will be mounted on the arms of the giant tools and delicately rotated inward to the point where—if they were the real components—they would be close enough to be assembled to the vacuum vessel sector positioned in the centre of the tool, as well as to thermal shield panels.

During the machine assembly phase, this "slow embrace" will be performed nine times—one for each sector of the doughnut-shaped vacuum vessel.

"The weight of the components and the very high accuracy required create very severe conditions," says Ryutaro Okugawa, the leader of the ITER Tooling & Engineering Group, which is overseeing the load test preparation.

Made of seven different steel-and-concrete modules, the dummies slightly exceed the weight of the actual coil but closely reproduce their centre of gravity and distribution of mass. (Click to view larger version...)
Made of seven different steel-and-concrete modules, the dummies slightly exceed the weight of the actual coil but closely reproduce their centre of gravity and distribution of mass.
First, the stiffness and rigidity of the seven-module loads needs to be confirmed. This will be achieved by lifting the dummies a few centimetres above the shop floor and measuring the stress on the tension bars—the so-called "Macalloys"—that keep the module together.

Then comes the hard part: each load will be lifted and upended using a 800-tonne mobile crane (during the actual assembly activities, a bespoke "upending tool" will be used) working in close coordination with the overhead cranes of the  Assembly Hall.

The mock loads will then be positioned with utmost precision on their dedicated supports within each tool in turn and attached to their respective upper and lower adjustment units.

For the 22-metre-high Titan undergoing testing, it will be time to slowly close its heavily loaded arms and practice—for the first time—the actual embrace of a 440-tonne vacuum vessel sector.


return to the latest published articles