Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cooling water system | The tanks within a tank

    Deep inside the bowels of the Tokamak Building, the entrance to one of most spectacular rooms of the whole installation resembles that of a broom cupboard. [...]

    Read more

  • ITER assembly | Last major assembly contract signed

    One year after finalizing two major machine assembly contracts, the ITER Organization has chosen the contractors who will carry out assembly and installation ac [...]

    Read more

  • ITER Science | The towering importance of data

    The most important product of ITER is data, which will be used to produce the information needed to build models for DEMO and commercial reactors—and much more. [...]

    Read more

  • Image of the week | In my arms!

    In late November, one part of the 'shell' that encloses every vacuum vessel sector—a right-hand outboard thermal shield panel—had been mounted on a giant pre-as [...]

    Read more

  • Brexit | The UK will remain part of ITER

    'It was a great Christmas present,' says Ian Chapman, head of the United Kingdom Atomic Energy Authority. Many in the ITER community would agree. The Brexit neg [...]

    Read more

Of Interest

See archived entries

Image of the week

12 pillars and counting

Two rows of pillars have now appeared at the top of the ITER Tokamak Building—12 out of 20 base pillars that will soon be topped by a second level of pillars, and finally the roof structure.

Elements of the crane hall roof structure—first pillars, then roof structure—are lifted at the end of the afternoon and into the night so as not to interfere with the movement of the worksite cranes during the day. (Click to view larger version...)
Elements of the crane hall roof structure—first pillars, then roof structure—are lifted at the end of the afternoon and into the night so as not to interfere with the movement of the worksite cranes during the day.
The crawler crane enters into action in late afternoon and continues on into the night, carefully lifting the 28-tonne, 13-metre-tall pillars some 45 metres above the platform to be bolted along either side of the Tokamak Building's concrete structure.

Two rows of 10 are planned. The lower pillars accommodate shelf-like platforms that will support the crane rails as they are extended out beyond the Assembly Hall; the second pillar segments—16-metre-tall upper pillars—will be installed next.

A few hundred metres away, sections of roof frame are being assembled on the ground. A second crawler crane will work in tandem with the first to lift these into place.

But for now, nearly every night a new pillar or two can be seen from the windows of the ITER Headquarters Building ...


return to the latest published articles