Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Construction | Art around every corner

    Most of us have experienced it. Turning a corner in one of the Tokamak Building galleries and looking up at the graphic pattern of embedded plates in the concre [...]

    Read more

  • Machine | Ensuring port plugs will work as planned

    The stainless steel plugs sealing off each Tokamak port opening are not only massive, they are also complex—carrying and protecting some of the precious payload [...]

    Read more

  • Networks | Ensuring real-time distributed computing at ITER

    Many of the control systems at ITER require quick response and a high degree of determinism. If commands go out late, the state of the machine may have changed [...]

    Read more

  • Fusion codes and standards | Award for ITER Japan's Hideo Nakajima

    Hideo Nakajima, a senior engineer at ITER Japan, has received an award from the Japan Society of Mechanical Engineers (JSME) for his contribution to the develop [...]

    Read more

  • Machine assembly | First magnet in place

    When it travelled the ITER Itinerary last year, or during cold tests in the onsite winding facility, poloidal field coil #6 (PF6) felt rather large and massive. [...]

    Read more

Of Interest

See archived entries

Assembly preparation

Off goes the lid

In the summer of 2017, a circular platform was installed inside of the large steel-and-concrete cylinder of the Tokamak pit. The 200-tonne structure was meant to protect the workers active in the lower levels while providing storage for activities above. The following year, the platform was hoisted some 20 metres to form a temporary roof, where it remained for two years. And finally, last week, the time had come to remove the massive "lid" to allow access to the pit in anticipation of the machine assembly phase. In two days, the 11 segments of the structure were dismantled, lifted and safely stored to be re-used at a later stage of ITER operations.

One of the smaller lid segments is being readied for lifting. In two days, the 11 segments of the structure were dismantled, lifted and safely stored to be re-used at a later stage of ITER operations (Click to view larger version...)
One of the smaller lid segments is being readied for lifting. In two days, the 11 segments of the structure were dismantled, lifted and safely stored to be re-used at a later stage of ITER operations
In the vast open space of the assembly theatre the powerful overhead cranes were back at work, lifting the lid's segments one by one, transporting them from one hall to the other, and delicately depositing them on the vehicles that would take them to storage—a regular flat-bed trailer for the smaller segments (10 to 20 tonnes), a dedicated self-propelled modular transporter for the two "half moons" weighing close to 80 tonnes each (more details in the image gallery below).

On its way to the self-propelled transport trailer, an 80-tonne half-moon segment passes over the upending tool. (Click to view larger version...)
On its way to the self-propelled transport trailer, an 80-tonne half-moon segment passes over the upending tool.
The intense activity in the crane hall, with several elevated platforms moving painters along the rafters just below the crane runway, plus space limitations in the adjacent assembly hall where the upending tool was being prepared for another set of tests, added constraints to the already challenging operation.

But the well-oiled team, once again, proved up to the task. Access to the Tokamak pit is now open to the overhead cranes.



return to the latest published articles