Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Neutral beam power supply | Lightning-power voltage

    In January 2021, preparatory works began for the construction of two large buildings designed to accommodate a unique set of electrical equipment. A little more [...]

    Read more

  • MITICA | Cryopump passes site acceptance tests

    Cryopumps, which play an essential role in ITER, are not what one has in mind when picturing a pump. A conventional pump creates negative pressure to suck in fl [...]

    Read more

  • Construction progress | Bird's eye views, three years apart

    Taken three years apart (February 2020-February 2023) these two aerial photographs provide a spectacular illustration of progress on the ITER construction site. [...]

    Read more

  • Tritium breeding | Korea and Europe enter partnership

    The future of fusion rests on the availably of two hydrogen isotopes, deuterium (one proton, one neutron) and tritium (one proton, two neutrons). Extracting deu [...]

    Read more

  • Diagnostic windows | Preserving the view and the vacuum

    Punctuating the inner surface of the vacuum vessel are many strategically placed windows that will be used by diagnostic systems to 'observe' the plasma. " [...]

    Read more

Of Interest

See archived entries

Assembly preparation

Off goes the lid

In the summer of 2017, a circular platform was installed inside of the large steel-and-concrete cylinder of the Tokamak pit. The 200-tonne structure was meant to protect the workers active in the lower levels while providing storage for activities above. The following year, the platform was hoisted some 20 metres to form a temporary roof, where it remained for two years. And finally, last week, the time had come to remove the massive "lid" to allow access to the pit in anticipation of the machine assembly phase. In two days, the 11 segments of the structure were dismantled, lifted and safely stored to be re-used at a later stage of ITER operations.

One of the smaller lid segments is being readied for lifting. In two days, the 11 segments of the structure were dismantled, lifted and safely stored to be re-used at a later stage of ITER operations (Click to view larger version...)
One of the smaller lid segments is being readied for lifting. In two days, the 11 segments of the structure were dismantled, lifted and safely stored to be re-used at a later stage of ITER operations
In the vast open space of the assembly theatre the powerful overhead cranes were back at work, lifting the lid's segments one by one, transporting them from one hall to the other, and delicately depositing them on the vehicles that would take them to storage—a regular flat-bed trailer for the smaller segments (10 to 20 tonnes), a dedicated self-propelled modular transporter for the two "half moons" weighing close to 80 tonnes each (more details in the image gallery below).

On its way to the self-propelled transport trailer, an 80-tonne half-moon segment passes over the upending tool. (Click to view larger version...)
On its way to the self-propelled transport trailer, an 80-tonne half-moon segment passes over the upending tool.
The intense activity in the crane hall, with several elevated platforms moving painters along the rafters just below the crane runway, plus space limitations in the adjacent assembly hall where the upending tool was being prepared for another set of tests, added constraints to the already challenging operation.

But the well-oiled team, once again, proved up to the task. Access to the Tokamak pit is now open to the overhead cranes.



return to the latest published articles