Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Thermal shield | Practising the embrace

    In the ITER Assembly Hall, fitting tests are underway on two outboard thermal shield panels. Once paired, the 11-metre-tall, silver-plated components will [...]

    Read more

  • Image of the week | This circle is for the ring

    Another concentric circle has been drawn at the bottom of the machine assembly pit, formed by the temporary supports recently installed for poloidal field coil [...]

    Read more

  • Feeders | Multi-lane thruways into the machine

    The ITER superconducting coils thrive on a simple diet of electrical power and cooling fluids. The industrial installation on site is scaled to provide both, bu [...]

    Read more

  • Cryostat Workshop | Top lid enters the stage

    In this vast workshop over the past five years, the different sections of the ITER cryostat have been assembled and welded under India's responsibility. The bas [...]

    Read more

  • Blanket first wall | Manufacturing kicks off in Europe

    For one of the most demanding technological components of the ITER machine—the first wall of the blanket—the European Domestic Agency Fusion for Energy made the [...]

    Read more

Of Interest

See archived entries

Deliveries

Two coils on their way

For the past five years, "highly exceptional loads" (HEL) have been successfully travelling along the ITER Itinerary to be delivered to the ITER site. As the project now enters machine assembly phase, a new category of components is heading to Saint-Paul-lez-Durance. Dubbed "super HEL," they combine exceptional value, size and weight and come with renewed challenges which the global health crisis makes even more daunting.

Procured by Europe and finalized in Italy, toroidal field coil #9 (TF9) is seen here on 23 March as it approaches the narrow Caronte Canal in Martigues. The massive load (600 tonnes) will reach the ITER site in the early morning of 17 April. Photo DAHER (Click to view larger version...)
Procured by Europe and finalized in Italy, toroidal field coil #9 (TF9) is seen here on 23 March as it approaches the narrow Caronte Canal in Martigues. The massive load (600 tonnes) will reach the ITER site in the early morning of 17 April. Photo DAHER
Two such components recently arrived at Marseille's industrial harbour Fos-sur-Mer, and will soon be delivered to the ITER site.

Procured by Europe and finalized in Italy, toroidal field coil #9 (TF9) was unloaded on 18 March and crossed the inland sea Etang-de-Berre five days later.

A second toroidal field coil (TF12), procured by Japan, left the port of Kobe on 7 March and arrived at Fos-sur-Mer on 7 April—one month later to the day.

Over the past five years, 75 HEL have been safely delivered to ITER. None, however, matched the dimensions and weight—20 metres long, slightly more than 10 metres wide, 600 tonnes with support frame and trailer—of these "Super HEL," the first in a series of two dozen truly exceptional loads to be delivered in the next few years.

One month to the day after it left the port of Kobe, Japan, on 7 March, coil #12 (TF12) arrived at Marseille's industrial harbour. The load will begin the last leg of its journey on 21 April and arrive at ITER four days later. Photo DAHER (Click to view larger version...)
One month to the day after it left the port of Kobe, Japan, on 7 March, coil #12 (TF12) arrived at Marseille's industrial harbour. The load will begin the last leg of its journey on 21 April and arrive at ITER four days later. Photo DAHER
To the challenges of transporting such behemoths over the 104-kilometre ITER Itinerary, the global health crisis has added extra constraints. The organization of the convoys, the logistics and the schedule all needed to be adapted to mitigate risk for the loads and guarantee optimal health and safety conditions for the personnel involved.

According to the latest information, the operation will unfold as follows: TF9 will leave its temporary staging area on the northern shore of Etang-de-Berre on 13 April, Easter Monday, and reach the ITER site in the early morning of 17 April. As soon as the component is unloaded, the trailer will be disassembled, shipped back to Berre by truck, and reassembled there. Ideally the trailer, by then loaded with TF12, could be ready to travel on 21 April and arrive at ITER in the early hours of Saturday 25 April.

ITER convoys do not travel on weekends or holidays, but an exception was made for this unique situation. "The French authorities, the gendarmerie, and the thruway operators have all been extremely supportive," says François Genevey, who manages ITER transport operations for the project's global logistics provider DAHER. "Everyone is aware of the importance and challenges of this double operation."



return to the latest published articles