Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

  • Education | 13th ITER International School announced

    The 13th ITER International School (IIS) will be held from 9 to 13 December in Nagoya hosted by National Institute for Fusion Science (NIFS), Japan. The subject [...]

    Read more

  • Open Doors Day | Having fun while discovering ITER

    A public event on Saturday 13 April draws a big crowd. It was a beautiful, summer-like day on Saturday 13 April. Perfect for a journey into ITER. Nearly 800 mem [...]

    Read more

  • Fusion world | Increased awareness in a changing landscape

    The world of fusion research is changing fast, and world leaders are taking notice. The large public projects that occupied centre stage for the past decades ar [...]

    Read more

Of Interest

See archived entries

Welding

Cryostat base and lower cylinder are now one

Procured by India, the ITER cryostat is composed of four sections: the base, the lower and upper cylinders, and the top lid. Once positioned inside the assembly pit, the different sections are welded together in order to form the perfectly leak-tight vacuum chamber that will act as a thermos, insulating the ultra-cold superconducting magnets from the outside environment.

The welding of the lower cylinder to the cryostat base began in October 2020 and was completed in the last week of March 2021. ''Throughout this six-month operation we were never outside tolerance,'' says mechanical engineer Vikas Dube. (Click to view larger version...)
The welding of the lower cylinder to the cryostat base began in October 2020 and was completed in the last week of March 2021. ''Throughout this six-month operation we were never outside tolerance,'' says mechanical engineer Vikas Dube.
Protected in a sealed cocoon, the upper cylinder has been in storage on the platform since April 2020. The cryostat base was lowered into the pit in May 2020, followed by the lower cylinder in August. As for the top lid, its 12 segments are being assembled and welded in the Cryostat Workshop.

The first in-pit welding operation—the welding of the lower cylinder to the cryostat base—began in October 2020 and lasted six months, including testing. Like all previous cryostat welding operations, it was performed by India's contractor MAN Energy Solutions (sub-contractor of cryostat segment manufacturer Larsen & Toubro).

Following a first phase of root welding by way of a technique known as "double operator" welding (one working from the inside, the other from the outside), nine specialists continued working simultaneously on the 90 metres of circumference, using more than 1.5 tonnes of filler material in the process.

Distortion monitoring was performed on a regular basis by way of 50 metrology targets distributed on the inner surface of the components. "Because of the heat that the welds generate, deformation inevitably occurs, but we have ways to minimize that. Margins are included by manufacturing design and throughout this six-month operation we were never outside tolerance," says Vikas Dube, a mechanical engineer in ITER In-Cryostat, Cryostat Thermal Shield, Auxiliaries Section.

A weld, however, is not considered final until it is tested. Beginning with visual inspection, the non-destructive examination process implements a series of tests ranging from the simple, like dye penetrant test examination, to the ultra-sophisticated like helium leak tests.

The final check consists of a dimensional inspection that compares the data from the welded components to the data that was recorded before the start of welding, as well as to the requirements from the manufacturing drawings. There again, "everything was within the limits," says Vikas.



return to the latest published articles