Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • A world in itself

    From a height of some 50 metres, you have the entire ITER worksite at your feet. The long rectangle of the Diagnostics Building stands out in the centre, with [...]

    Read more

  • US completes toroidal field deliveries for ITER

    The US Domestic Agency achieved a major milestone in February by completing the delivery of all US-supplied toroidal field conductor to the European toroidal fi [...]

    Read more

  • Thin diagnostic coils to be fitted into giant magnets

    Last week was marked by the first delivery of diagnostic components—Continuous External Rogowski (CER) coils—from the European Domestic Agency to the ITER Organ [...]

    Read more

  • Addressing the challenge of plasma disruptions

    Plasma disruptions are fast events in tokamak plasmas that lead to the complete loss of the thermal and magnetic energy stored in the plasma. The plasma control [...]

    Read more

  • Blending (almost) seamlessly into the landscape

    Located in the foothills of the French Pre-Alps, the ITER installation blends almost seamlessly into the landscape. The architects' choice ofmirror-like steel c [...]

    Read more

Of Interest

See archived articles

Complexity that works

-Robert Arnoux

Frank Briscoe, Director of F4E and IO Director-General Osamu Motojima sign the agreement that makes the ITER site available to Fusion for Energy. Also present are Harry Tuinder, Legal Adviser to the DG and Tim Watson, Head of the Civil Construction & Site Support (CCS) Office. (Click to view larger version...)
Frank Briscoe, Director of F4E and IO Director-General Osamu Motojima sign the agreement that makes the ITER site available to Fusion for Energy. Also present are Harry Tuinder, Legal Adviser to the DG and Tim Watson, Head of the Civil Construction & Site Support (CCS) Office.
A lot of legal work has been performed these past weeks at the ITER Organization.

On Tuesday 6 July the ITER site, while remaining CEA property, was made available by notary deed to the ITER Organization. Less than three weeks later, ITER and CEA legal representatives met again in Paris to sign a sale deed for the existing site installations (Visitor Centre, technical buildings, storm basins, etc.).

By way of these two deeds, ITER now holds "full rights" to the land and buildings and will retain them for the duration of the ITER Agreement - that is, until 24 October 2042.

While the overall responsibility of the ITER site and existing buildings rests with the ITER Organization (IO), actual construction work will be conducted mainly by Agence ITER France (AIF) for the future IO Headquarters; and by Fusion for Energy (F4E) for all the buildings that constitute the ITER facility.

On 26 July, IO Director-General Kaname Ikeda proposed to Jérôme Pamela, Director of AIF, to "delegate temporarily" -  meaning until completion of the Headquarters building by the end of December 2011 - the responsibility of health, safety, environment protection and logistics on the ITER worksite to AIF/CEA.

Three days later, Kaname Ikeda's successor Prof. Osamu Motojima and Frank Briscoe, Director of F4E, signed an agreement that made the ITER platform available to F4E in order to "undertake the construction of the ITER buildings and site infrastructure."

Complicated? "In appearance only," says Harry Tuinder, the Legal Advisor to the ITER Director-General. "Every large construction site — and ITER is one of the largest in the world — has to face this kind of challenge. We have set up an ITER Site Steering Committee that will coordinate, under our responsibility, AIF and F4E's activities on the worksite. Everything is now ready, and earlier than we expected, to enter the construction phase."


return to the latest published articles