Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

Complexity that works

Robert Arnoux

Frank Briscoe, Director of F4E and ITER Director-General Osamu Motojima sign the agreement that makes the ITER site available to Fusion for Energy. Also present are Harry Tuinder, Legal Adviser to the Director-General and Tim Watson, Head of the Civil Construction & Site Support Office. (Click to view larger version...)
Frank Briscoe, Director of F4E and ITER Director-General Osamu Motojima sign the agreement that makes the ITER site available to Fusion for Energy. Also present are Harry Tuinder, Legal Adviser to the Director-General and Tim Watson, Head of the Civil Construction & Site Support Office.
A lot of legal work has been performed these past weeks at the ITER Organization.

On Tuesday 6 July the ITER site, while remaining CEA property, was made available by notary deed to the ITER Organization. Less than three weeks later, ITER and CEA legal representatives met again in Paris to sign a sale deed for the existing site installations (Visitors Centre, technical buildings, storm basins, etc.).

By way of these two deeds, ITER now holds "full rights" to the land and buildings and will retain them for the duration of the ITER Agreement—that is, until 24 October 2042.

While the overall responsibility of the ITER site and existing buildings rests with the ITER Organization, actual construction work will be conducted mainly by Agence ITER France for the future Headquarters building; and by the European Domestic Agency (F4E) for all the buildings that constitute the ITER facility.

On 26 July, ITER Director-General Kaname Ikeda proposed to Jérôme Pamela, Director of Agence Iter France, to "delegate temporarily"—meaning until completion of the Headquarters building by the end of December 2011—the responsibility of health, safety, environment protection and logistics on the ITER worksite to Agence Iter France/CEA.

Three days later, Kaname Ikeda's successor Director-General Osamu Motojima and Frank Briscoe, Director of F4E, signed an agreement that made the ITER platform available to F4E in order to "undertake the construction of the ITER buildings and site infrastructure."

Complicated? "In appearance only," says Harry Tuinder, the Legal Advisor to the ITER Director-General. "Every large construction site—and ITER is one of the largest in the world—has to face this kind of challenge. We have set up an ITER Site Steering Committee that will coordinate, under our responsibility, Agence Iter France and F4E's activities on the worksite. Everything is now ready, and earlier than we expected, to enter the construction phase."


return to the latest published articles