Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Open Doors Day | An intense and unforgettable experience

    Saturday was Jacques's birthday. At age 90, the long-retired engineer from Aix-en-Provence had only one item on his wish list: to visit ITER for a third time an [...]

    Read more

  • Power conversion | A potent illustration of the "One ITER" spirit

    Europe made the buildings; the piping came from India; China and Korea provided the transformers; Russia manufactured the massive 'busbar' network. The ITER Org [...]

    Read more

  • Fusion world | Upgrade completed on DIII-D tokamak

    The DIII-D National Fusion Program (US) has completed a series of important enhancements to its fusion facility, providing researchers with several first-of-a-k [...]

    Read more

  • Vacuum lab | Ensuring leak test sensitivity

    A helium leak test is one of several factory acceptance tests planned for the sectors of the ITER vacuum vessel before they are shipped to ITER. In a vacuum lab [...]

    Read more

  • Bookmark | The Future of Fusion Energy

    To write about fusion is to walk a fine line between the temptation of lyricism and the arid demands of scientific accuracy. Whereas the general media tends to [...]

    Read more

Of Interest

See archived entries

Action!

Robert Arnoux

A power shovel removes the first of some 230,000 cubic metres from the Tokamak Pit. (Click to view larger version...)
A power shovel removes the first of some 230,000 cubic metres from the Tokamak Pit.
The first days of August in southern France are usually very quiet. This is the heart of the summer holiday season; half the shops and businesses are closed and every serious decision has to be postponed until la rentrée, the first weeks of September when life finally gets back to normal.

On a small, 42 hectare-wide area of southern France, however, the first week of August was marked by renewed activity.

Bulldozers, scrapers and power shovels were back on the ITER platform: under the responsibility of the European Domestic Agency F4E, work began in the Tokamak Pit and on the 14,000-square-metre area that will host the huge Poloidal Field Coils Winding Facility.

On Wednesday 4 August , after some preparatory works had been done during the previous week, a lone power shovel began removing the top soil from the Tokamak Pit—the first of some 230,000 cubic metres that will have to be extracted  in order to make room for the installation.

Operations and safety on the ITER platform are being carefully coordinated by the ENGAGE Consortium and the French company APAVE. (Click to view larger version...)
Operations and safety on the ITER platform are being carefully coordinated by the ENGAGE Consortium and the French company APAVE.
In a little more than three weeks, blasting specialists will move in for two months. Explosives will be used to blast some of the rock layer at an average rate of 4,000 cubic metres per day.

Some 250 metres away, bulldozers and scrapers were busy levelling the poloidal field coils assembly area and preparing a smooth "sub-base" on top of which a 30- to 40 centimetre-thick concrete floor slab will be poured in about a month.

Operations on the ITER platform are being carefully coordinated under the authority of the ENGAGE Consortium and, as far as Health & Safety are concerned, by the French company APAVE.

Bulldozers and scrapers are busy levelling the 14,000-square-metre area that will host the huge Poloidal Field Coils Winding Facility. (Click to view larger version...)
Bulldozers and scrapers are busy levelling the 14,000-square-metre area that will host the huge Poloidal Field Coils Winding Facility.
Coordination will be crucial starting at the end of the month, when rock will be blasted here and concrete poured there .... It has been decided that blasting will be performed during lunch break and concrete poured in the afternoon, then left to harden during the night.

"This is the first actual work en route to First Plasma," says Ben Slee, Deputy Head of Site Building and Power Supplies at F4E. "It is essential to keep the schedule ...."

While actual work on the future ITER Headquarters and related buildings will only start in September, preliminary earthworks have been ongoing for a couple of days below the northeast corner of the platform.

Agence Iter France, who is responsible for construction, expects to deliver the buildings (co-financed by France and F4E) by mid-2012.


return to the latest published articles