Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Component repair

With contracts in place, the repair campaign has begun

Contracts were awarded this summer to the companies that will carry out the repair/refurbishment of the ITER thermal shield and vacuum vessel sectors. Teams deployed on site are already executing the first steps of the campaign.

In its investigations to find the most optimal repair strategies for the thermal shield and vacuum vessel sectors, the ITER team worked for many months with experts from the ITER Domestic Agencies, professional organizations from the ITER Members, and research institutes such as CEA, CERN and professional welding institutes—as well as industrial partners to test its assumptions through mock-ups and trials. (Photo: January 2023) (Click to view larger version...)
In its investigations to find the most optimal repair strategies for the thermal shield and vacuum vessel sectors, the ITER team worked for many months with experts from the ITER Domestic Agencies, professional organizations from the ITER Members, and research institutes such as CEA, CERN and professional welding institutes—as well as industrial partners to test its assumptions through mock-ups and trials. (Photo: January 2023)
One year ago, the first of nine vacuum vessel sector modules (#6) had been transferred in the Tokamak pit and two others (#7 and #8) were in preparation in sub-assembly tooling in the Assembly Hall, where the 440-tonne sectors were being matched with thermal shield panels and toroidal field coils.

The discovery of major defects in two of the components making up these sector modules brought vacuum vessel sub-assembly works to a halt and mobilized resources inside the ITER Organization to identify the root causes of the defects and to explore different repair options. The ITER team worked with experts from the ITER Domestic Agencies, professional organizations from the ITER Members, and research institutes such as CEA, CERN and professional welding institutes to arrive at its final strategy, and with industrial partners to test its assumptions through mock-ups and trials. The repair campaign would be handled under three separate contracts—one for the repair of thermal shield panels, a second for the manufacturing of new thermal shield panels, and a third for vacuum vessel bevel repair.

Working in close collaboration with the technical and legal teams, the ITER Procurement & Contracts Division was able to launch restricted tenders early in 2023, and conclude all negotiations in time to meet the tight schedule established by ITER management.

Outboard segments of thermal shield await disassembly by contractor teams at one end of the Poloidal Field Coils Winding Facility on site. Two sets will be repaired at the premises of INOX India, and returned to ITER; the strategy for five other sets is being defined. (Photo: August 2023) (Click to view larger version...)
Outboard segments of thermal shield await disassembly by contractor teams at one end of the Poloidal Field Coils Winding Facility on site. Two sets will be repaired at the premises of INOX India, and returned to ITER; the strategy for five other sets is being defined. (Photo: August 2023)
The vacuum vessel thermal shield, which confines the radiation heat load from the vessel and keeps it from being transferred to the magnets operating at 4.5K, is actively cooled by gaseous helium running through a network of cooling tubes welded to the panels. After "stress corrosion cracking" was identified on three sets of panels—and determined to be a likely risk for the others—the decision was made to replace the cooling fluid pipes on all nine sets of vacuum vessel thermal shield.

"The structural integrity assuring the leak-tight configuration of these pipes—all 23 kilometres of them—is critical because gases and liquids will find the tiniest breach in a structure under vacuum," explains Sergio Orlandi, Head of the ITER Construction Project. "Even submicron cracks can alter vacuum quality and degrade machine performance."

Two strategies were established by the expert groups. For thermal shield sectors showing no sign of stress corrosion cracking, the panels could be repaired. Repair would entail dismantling the sets into individual panels, removing all cooling pipes, grinding and polishing to remove the silver coating from the surface and to remove up to approximately ~3mm of base material from the panels in the area of the cooling pipes, and  finally re-attaching new pipes with stitch welding (and without silver coating). For thermal shield sectors already compromised by damage, complete re-fabrication was the preferred option. For both contracts, companies would be responsible for developing the methods and practices to achieve ITER requirements. The ITER Organization is supplying the new pipes.

  • Thermal shield repair will be performed by INOX India. The contract was signed on 29 June for the repair of two sets of vacuum vessel thermal shield, and the optional repair of five others. The panels for these two sets will be disassembled at ITER, shipped to INOX premises for repair, tested for leaks in the factory, then shipped back to the ITER site for reassembly and testing by the contractor. A team from INOX is already mobilized on the ITER site for disassembly. Qualification activities on a mockup are also underway at the INOX India workshop under ITER Organization supervision.
  • Thermal shield replacement will be performed by SamHong Heavy Machinery (Korea). The contract was signed on 30 June for the manufacture of two sets of vacuum vessel thermal shield. The company is required to perform qualification of the whole fabrication process through mock-ups. It will also procure raw material, carry out all aspects of manufacturing, perform factory testing to ensure leak tightness, and deliver the components to ITER. The kick-off meeting has already taken place.


The SIMIC/Ansaldo consortium will repair the non-conformities on sectors #6 and #7 while they are suspended in sector sub-assembly tooling in the Assembly Hall. The bevel regions will be re-worked through a combination of build-up (building up material through manual welding) and shaving (removing excess material through machining). (Photo: January 2023) (Click to view larger version...)
The SIMIC/Ansaldo consortium will repair the non-conformities on sectors #6 and #7 while they are suspended in sector sub-assembly tooling in the Assembly Hall. The bevel regions will be re-worked through a combination of build-up (building up material through manual welding) and shaving (removing excess material through machining). (Photo: January 2023)
Dimensional non-conformities were found in the bevel (field joint) region of the three vacuum vessel sectors that have been delivered to ITER (#6, #7 and #8), with particularly severe variance against nominal geometry in sector #8. Left unrepaired, these non-conformities would compromise the access and operation of the bespoke automated welding tools planned for the in-pit welding of the sectors. The ITER Organization approach to repair is to re-work the bevels through a combination of building up material through manual welding and shaving excess material down through machining.

"From the start, our investigation teams stressed the importance of preferring machining over build-up wherever possible in order to minimize build-up as a whole. This is because added material is more susceptible to welding defects generating shrinkage in the sectors' configuration. That is a first important element of our repair strategy for the vacuum vessel," says Orlandi. "The second is that we need to take an integrated approach in the investigation of adjacent sectors' geometry. Instead of considering a sector's geometry only against its nominal manufacturing drawings, we have to consider each sector's configuration in relation to the adjacent sectors on either side to which it will be jointed through spliced plates with automatic welding." This approach informed the technical specifications that were prepared for the restricted tender.

  • Vacuum vessel bevel repair will be carried out at the ITER site by a consortium comprising the Italian firms SIMIC S.p.A. and Ansaldo Nucleare. The contract is awarded for the repair of sector #6 and #7 (vertically, in sector sub-assembly tooling in the Assembly Hall), with an option for the repair of sector #8 (horizontally, in the former Cryostat Workshop). The industrial partner must develop its design solution (including the balance between build up and machining), qualify its design solution and tools with mock-ups, perform the repairs, and ensure metrology and non-destructive examination. The contract was signed on 4 August and the kick-off meeting is planned in the first week of September. The teams will start with the repair of sector #7.


The ITER Organization has formed dedicated task force (also involving specialists in the European Agency Fusion for Energy) that has all of the requisite competencies to follow, control and manage the repair works. The ITER Newsline will be meeting with this team in the coming days and weeks to produce a photo reportage on repair activities underway.



return to the latest published articles