Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

Final design review for magnet feeders

Neil Mitchell, Head of the ITER Magnets Division

The final design review for the ITER feeders took place this week. (Click to view larger version...)
The final design review for the ITER feeders took place this week.
The magnet feeder final design review was held in Cadarache this week on 20-22 September. This important milestone marks the conclusion of an intense team effort of the ITER Organization and the Institute of Plasma Physics at the Chinese Academy of Science (ASIPP) to complete the design of the feeders, and opens the door to signing the Procurement Arrangement with the Chinese Domestic Agency.

Overall view of magnet feeder system. (Click to view larger version...)
Overall view of magnet feeder system.
The feeders are the lift-lines to the ITER magnet systems. They convey and regulate the cryogenic liquids to cool and control their temperature. They also connect the magnets to their power supply.  The feeders thus represent a critical component interfacing the magnets with other vital parts of the machine.

68kA HTS lead prototype manufactured and tested at ASIPP (Click to view larger version...)
68kA HTS lead prototype manufactured and tested at ASIPP
"The feeders are not as glamorous as the magnets," Chairman Philippe Lebrun said, Project Manager of the Large Hadron Collider at CERN, "but they are vital elements that have many interfaces. They therefore tend to reveal interface issues and that is what is happening right here."

The review was preceded by two pre-reviews, one on the high temperature superconducting (HTS) current leads and one on the assembly of the feeders into the cryostat and the building galleries. The feeders are the final magnet component to go through a final design review and will be the last magnet Procurement Arrangement to be signed. Their completion has been delayed due to the need to focus the very limited magnet division resources onto the magnets themselves, which have longer manufacturing lead times.‬‪

Integration of the poloidal field feeder within the cryostat. (Click to view larger version...)
Integration of the poloidal field feeder within the cryostat.
On day three, the reviewers presented their overall summary, noting that although a lot of work remains to be done before the Procurement Arrangement can be signed in three months, the foundations have been established and there are no "show stoppers" seen to the successful completion of the Procurement Arrangement documentation on this timescale.‬‪


return to the latest published articles