  • ITER DNA | A "case" study...

    In December last year, and again this year in early May, pre-welding fitting tests demonstrated that steel components as tall as a four-storey building (and wei [...]

    Read more

  • First plasma| Temporary in-vessel protection

    The vacuum vessel, the operating theatre of the ITER machine, needs to be protected against possible damage from the hot plasma at any given time during its ope [...]

    Read more

  • Divertor cassettes | Successful prototypes open way to series

    Before embarking on the fabrication of the 54 complex steel structures that will form a ring at the bottom of the ITER machine—the divertor cassettes—the Europe [...]

    Read more

  • Images of the week | Titan tool 90 percent complete

    Towering 22 metres above ground and weighing approximately 800 tonnes, the twin sector sub-assembly tools (SSAT) are formidable handling machines that will be u [...]

    Read more

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

Of Interest

See archived articles

Rock blasting is nearing completion

Taiger Murphy, Civil Engineering Technician

The first phase of the Tokamak excavation is nearing completion. (Click to view larger version...)
The first phase of the Tokamak excavation is nearing completion.
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings. (Click to view larger version...)
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings.
Tokamak Complex excavation and support structure:
Ongoing rock blasting and excavation is continuing in the area of the future Tokamak Complex. The first phase of blasting is nearing completion.

Poloidal field coil fabrication building:
Concrete slab pours are continuing. In tandem, concurrent activities are progressing westwards along the building, including work on the column footing installation, concrete column reinforcement and cast-in-place concrete placement is continuing for the above-ground structure.

Permanent ITER Headquarters ('Annex Buildings'):
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters buildings. Ground foundation anchors and other ground preparation works are continuing.

Site infrastructure:
Authorization to access the on-platform water supply and on-platform electrical power has been achieved for use in one of the first major building construction contracts (Poloidal Field Coils Winding Facility).