Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Towards DEMO | What will the blanket teach us?

    We often hear about the scientific ideas ITER is designed to confirm, but the project also has an important role as a technology demonstrator. The blanket is a [...]

    Read more

  • Summer works | A new chapter opens

    Notice anything? Yes, the giant poster (25 x 50 m) on the temporary wall of the Assembly Hall has been removed. Displaying a cutaway of the ITER Tokamak, it had [...]

    Read more

  • Image of the week | On the thruway from Hefei to Shanghai

    Over the next four years, China will be shipping approximately 100 large components for the magnet feeder system, adding up to 1,600 tonnes of equipment in all. [...]

    Read more

  • India | Modi praises ITER at UNESCO

    In August, while on official visit to France at the invitation of President Emmanuel Macron, Prime Minister Narendra Modi of India shared his vision of cooperat [...]

    Read more

  • Vacuum technology | Record-breaking sealing performance

    The ITER vacuum vessel, its ports and port extensions, and port plugs all provide the vacuum boundary and first safety confinement barrier of the ITER machine. [...]

    Read more

Of Interest

See archived entries

Rock blasting is nearing completion

Taiger Murphy, Civil Engineering Technician

The first phase of the Tokamak excavation is nearing completion. (Click to view larger version...)
The first phase of the Tokamak excavation is nearing completion.
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings. (Click to view larger version...)
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings.
Tokamak Complex excavation and support structure:
Ongoing rock blasting and excavation is continuing in the area of the future Tokamak Complex. The first phase of blasting is nearing completion.

Poloidal field coil fabrication building:
Concrete slab pours are continuing. In tandem, concurrent activities are progressing westwards along the building, including work on the column footing installation, concrete column reinforcement and cast-in-place concrete placement is continuing for the above-ground structure.

Permanent ITER Headquarters ('Annex Buildings'):
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters buildings. Ground foundation anchors and other ground preparation works are continuing.

Site infrastructure:
Authorization to access the on-platform water supply and on-platform electrical power has been achieved for use in one of the first major building construction contracts (Poloidal Field Coils Winding Facility).