  • Neighbours | In goes the antenna

    Just a short distance from the ITER site, the Institute for Magnetic Fusion Research (IRFM) is modifying the Tore Supra plasma facility which, once transformed, [...]

    Read more

  • Remote handling | Off-site test facility for design evaluation

    Through a technical collaboration established between the ITER Organization and the UK Atomic Energy Authority (UKAEA) in 2017, the UKAEA's centre for Remote Ap [...]

    Read more

  • Poloidal field coils | A tailor-made ring

    They work like tailors, carefully taking measurements and cutting immaculate fabric with large pairs of scissors. But they're not making a white three-piece sui [...]

    Read more

  • Fusion world | Record results at KSTAR

    Experiments in the Korean tokamakKSTAR in 2017 achieved record-length periods of ELM suppression by the application of three-dimensional magnetic fields with in [...]

    Read more

  • JT-60 SA| Cryostat ready for Europe-Japan tokamak

    The cryostat vessel body of the JT-60SA tokamakhas been successfully manufactured and pre-assembled at a factory in Spain, and will soon be transferred to the J [...]

    Read more

Of Interest

See archived articles

Rock blasting is nearing completion

Taiger Murphy, Civil Engineering Technician

The first phase of the Tokamak excavation is nearing completion. (Click to view larger version...)
The first phase of the Tokamak excavation is nearing completion.
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings. (Click to view larger version...)
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings.
Tokamak Complex excavation and support structure:
Ongoing rock blasting and excavation is continuing in the area of the future Tokamak Complex. The first phase of blasting is nearing completion.

Poloidal field coil fabrication building:
Concrete slab pours are continuing. In tandem, concurrent activities are progressing westwards along the building, including work on the column footing installation, concrete column reinforcement and cast-in-place concrete placement is continuing for the above-ground structure.

Permanent ITER Headquarters ('Annex Buildings'):
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters buildings. Ground foundation anchors and other ground preparation works are continuing.

Site infrastructure:
Authorization to access the on-platform water supply and on-platform electrical power has been achieved for use in one of the first major building construction contracts (Poloidal Field Coils Winding Facility).