Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Computer-Aided Design | A new platform with Australia

    In September 2016, the signature of a Cooperation Agreement between the Australian Nuclear Science and Technology Organisation (ANSTO) and the ITER Organization [...]

    Read more

  • Ten years later | A prodigious adventure

    ITER began its existence as an aspiration in the early 1980s, as actors in the fusion community called for the joint machine that would demonstrate the feasibil [...]

    Read more

  • Image of the week | An impromptu visit

    Afteraddressing the UN Climate Change Conference on 15 November, French President Emmanuel Macron toured thecolourful COP23 exhibition zone. It was towards the [...]

    Read more

  • Cryoplant | How to install a compressor

    In order to properly install a helium compressor skid on its concrete pad, you need to start with a large push broom to sweep away the dust that inevitably accu [...]

    Read more

  • Magnetic system | Nine rings to fight the force

    Work on the pre-compression ringsof the ITER magnet system progresses in Europe, where work on a full-scale prototype is underway. These technically challenging [...]

    Read more

Of Interest

See archived articles

Rock blasting is nearing completion

Taiger Murphy, Civil Engineering Technician

The first phase of the Tokamak excavation is nearing completion. (Click to view larger version...)
The first phase of the Tokamak excavation is nearing completion.
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings. (Click to view larger version...)
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings.
Tokamak Complex excavation and support structure:
Ongoing rock blasting and excavation is continuing in the area of the future Tokamak Complex. The first phase of blasting is nearing completion.

Poloidal field coil fabrication building:
Concrete slab pours are continuing. In tandem, concurrent activities are progressing westwards along the building, including work on the column footing installation, concrete column reinforcement and cast-in-place concrete placement is continuing for the above-ground structure.

Permanent ITER Headquarters ('Annex Buildings'):
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters buildings. Ground foundation anchors and other ground preparation works are continuing.

Site infrastructure:
Authorization to access the on-platform water supply and on-platform electrical power has been achieved for use in one of the first major building construction contracts (Poloidal Field Coils Winding Facility).



return to the latest published articles