  • Making remote handling less remote

    Over a wet and windy three-day period on the ITER site in November, around 90 representatives of the ITER Organization, the Domestic Agencies of Europe and Japa [...]

    Read more

  • The framework for sharing ITER intellectual property

    In signing the ITER Agreement in 2006, the seven ITER Members were agreeing not only to share in the costs of constructing and operating the ITER facility, but [...]

    Read more

  • Wendelstein achieves ultra-precise magnetic topology

    A recent article in the online journal Nature Communications confirms that the complex topology of the magnetic field of Wendelstein 7-X—the world's largest ste [...]

    Read more

  • The Matrix, rigid and fluid

    A fast-growing array of structures and buildings has been emerging across the ITER worksite platform under the control and supervision of the European Domestic [...]

    Read more

  • By road, river and sea

    They travelled by road from the Air Liquide factory near Grenoble, sailed down the Rhône River from Lyon and entered the Mediterranean to the east of Fos-sur-Me [...]

    Read more

Of Interest

See archived articles

Rock blasting is nearing completion

-Taiger Murphy, Civil Engineering Technician

The first phase of the Tokamak excavation is nearing completion. (Click to view larger version...)
The first phase of the Tokamak excavation is nearing completion.
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings. (Click to view larger version...)
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings.
Tokamak Complex Excavation and Support Structure:
Ongoing rock blasting and excavation is continuing in the area of the future Tokamak Complex. The first phase of blasting is nearing completion.

Poloidal Field Coil Fabrication Building:
Concrete slab pours are continuing. In tandem, concurrent activities are progressing westwards along the building, including work on the column footing installation, concrete column reinforcement and cast-in-place concrete placement is continuing for the above-ground structure.

Permanent Iter Headquarters ('Annex Buildings'):
Concrete placement work has begun for the foundation at the west end of the building for the future permanent ITER Headquarters Buildings. Ground foundation anchors and other ground preparation works are continuing.

Site Infrastructure:
Authorization to access the on-platform water supply and on-platform electrical power has been achieved for use in one of the first major building construction contracts (PF Coil).