  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

Russia completes TF Conductor Dummy for testing

Alexander Petrov, RF ITER Domestic Agency

The 760 metres of toroidal field copper dummy conductor spooled on a transport solenoid. (Click to view larger version...)
The 760 metres of toroidal field copper dummy conductor spooled on a transport solenoid.
August 2011 turned out to be a hot time for Russian cable manufacturers who were able to honour an important milestone in the production of toroidal field conductors for ITER: the Russian Scientific Research and Development Cable Institute JSC VNIIKP completed the manufacture of 760 metres of toroidal field copper dummy conductor.

The conductors for ITER's magnet system are at the "heart" of one of the key elements of the future Tokamak and, as such, are receiving much attention from the Russian and ITER Organization experts who regularly inspect the conductor manufacturing processes in Moscow, Glazov and Podolsk.

The workshop at the Russian Scientific Research and Development Cable Institute JSC VNIIKP in Moscow. (Click to view larger version...)
The workshop at the Russian Scientific Research and Development Cable Institute JSC VNIIKP in Moscow.
To pass this critical milestone, the Russian Domestic Agency (RF-DA) team had to come a long way. To prepare for the manufacture of superconducting cables for ITER, the RF-DA reconfigured Russia's industrial infrastructure under the guidance of the Bochvar Institute (Moscow) and JSC VNIIKP. The development of the JSC ChMZ production facility in Glazov, beginning in 2004, required the purchase and installation of the equipment and technology necessary to fulfill extraordinary complicated, filigree work operations.

The manufacture of 760 metres of toroidal field copper dummy conductor is definitely a significant step forward, showing that with time and effort ... fine results can be achieved! This first copper dummy unit length will be used to qualify the conductors' manufacturing processes, including qualification of cabling, jacket welding, cable pull-through for an assembled jacket length, compaction, and spooling of the conductor. The final steps of process—compaction and spooling into a 4-metre transport solenoid—were completed in August.

Ready to roll: the brand-new jacketing line in Protvino. (Click to view larger version...)
Ready to roll: the brand-new jacketing line in Protvino.
With acceptance of the copper dummy conductor comes the finalization of jacketing line commissioning and the beginning of mass production. The dummy will be transported to Italy where it will be tested and qualified, after which we will be able to state that Russia is completely ready for producing toroidal field conductors for ITER ... which sounds really good! 


return to the latest published articles