Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

760-metre dummy conductor fabricated at ASIPP

Wu Yu, Institute of Plasma Physics at the Chinese Academy of Science (ASIPP)

The conductor passing its acceptance test. (Click to view larger version...)
The conductor passing its acceptance test.
A big milestone was achieved on 2 October when the Institute of Plasma Physics at the Chinese Academy of Science (ASIPP) completed the assembly and testing of the first 760 metres of toroidal field dummy conductor.

This is a meaningful step for ITER China: now, according to the Procurement Arrangement, the conductor will be divided into two pieces. One hundred metres of the 760-metre-long conductor will be delivered to the European Domestic Agency and the remaining 660 metres will be delivered to the Japanese Domestic Agency where further testing will be performed for the coil manufacturing.
 
China will supply 7.51 percent of ITER's toroidal field conductors, whose procurement is shared by six Domestic Agencies. With the support of the Chinese Domestic Agency and the ITER Organization, ASIPP contracted with domestic enterprises and institutes to develop the related engineering work and technology. ASIPP established a quality management system; built three conductor assembly lines; and completed research, installation and commissioning of the manufacturing equipment. Three short samples (TFCN1, TFCN2, TFCN3) have all been tested in the Sultan test facility in Switzerland where they met ITER Organization requirements and passed the obligatory quality checks.

A team from the Chinese Domestic Agency, led by Director Luo Delong (centre), witnesses the welding of the dummy conductor. (Click to view larger version...)
A team from the Chinese Domestic Agency, led by Director Luo Delong (centre), witnesses the welding of the dummy conductor.
Conductor integrating began on 14 September with the section welding of the conduit, non-destructive examination, cable insertion, compaction, and spooling. At each stage—up to the final acceptance test—representatives from the Chinese Domestic Agency and the ITER Organization were present.

We would like to express our special thanks to colleagues at both of these institutions for all their support and the spirit of cooperation that they have demonstrated over these past five years. We hope to continue in that spirit.


return to the latest published articles