Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Summer postcards from the ITER worksite

    The latest harvest of ITER construction photos may be taken from the same point—the tallest crane on site—but there is always an abundance of new detail to be g [...]

    Read more

  • The ring fortress

    ITER'ssteel-and-concretebioshield has become the definingfeature of Tokamak Complex construction. Twolevels only remain to be poured (out of six). It is a 'rin [...]

    Read more

  • The wave factory

    A year ago, work was just beginning on the steel reinforcement for the building's foundation slab. The Radio Frequency Heating Building is now nearing the last [...]

    Read more

  • It's all happening inside

    Since the giant poster was added to the Assembly Hall's completed exterior in June 2016 the building has lookedfrom afar like a finished project. Butinside, tea [...]

    Read more

  • Along skid row

    They look like perfectly aligned emergency housing units. But of course they're not: the 18 concrete structures in the ITER cryoplant are massive pads that will [...]

    Read more

Of Interest

See archived articles

760-metre dummy conductor fabricated at ASIPP

-Wu Yu, Institute of Plasma Physics at the Chinese Academy of Science (ASIPP)

The conductor passing its acceptance test. (Click to view larger version...)
The conductor passing its acceptance test.
A big milestone was achieved on 2 October when the Institute of Plasma Physics at the Chinese Academy of Science (ASIPP) completed the assembly and testing of the first 760 metres of toroidal field dummy conductor.

This is a meaningful step for ITER China: now, according to the Procurement Arrangement, the conductor will be divided into two pieces. One hundred metres of the 760-metre-long conductor will be delivered to the European Domestic Agency and the remaining 660 metres will be delivered to the Japanese Domestic Agency where further testing will be performed for the coil manufacturing.
 
China will supply 7.51 percent of ITER's toroidal field conductors, whose procurement is shared by six Domestic Agencies. With the support of the Chinese Domestic Agency and the ITER Organization, ASIPP contracted with domestic enterprises and institutes to develop the related engineering work and technology. ASIPP established a quality management system; built three conductor assembly lines; and completed research, installation and commissioning of the manufacturing equipment. Three short samples (TFCN1, TFCN2, TFCN3) have all been tested in the Sultan test facility in Switzerland where they met ITER Organization requirements and passed the obligatory quality checks.

A team from the Chinese Domestic Agency, led by Director Luo Delong (centre), witnesses the welding of the dummy conductor. (Click to view larger version...)
A team from the Chinese Domestic Agency, led by Director Luo Delong (centre), witnesses the welding of the dummy conductor.
Conductor integrating began on 14 September with the section welding of the conduit, non-destructive examination, cable insertion, compaction, and spooling. At each stage—up to the final acceptance test—representatives from the Chinese Domestic Agency and the ITER Organization were present.

We would like to express our special thanks to colleagues at both of these institutions for all their support and the spirit of cooperation that they have demonstrated over these past five years. We hope to continue in that spirit.


return to the latest published articles