Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • 23rd ITER Council | Pace and performance on track

    Working as an integrated team, the ITER Organization and seven Domestic Agencies are continuing to meet the project's demanding schedule to First Plasma in 2025 [...]

    Read more

  • Fusion Doctors | ITER hosts the future

    For three days last week, the ITER building was brimming with energy, inspiration and enthusiasm. One hundred and thirty-five young fusion aficionados took over [...]

    Read more

  • Fusion world | What's next for the stellarator?

    Earlier this year, the Wendelstein 7-X stellarator fusion project reported record achievements from its most recent experimental campaign. Newsline spoke with t [...]

    Read more

  • Metrology and the ITER machine | Perfectly planned points

    Inside of the Tokamak Complex, a network of 2,000 small 'fiducial target nests' will provide the reference datum for the dimensional control and alignment of ma [...]

    Read more

  • Breaking news | First component installed next week

    In the third week of November, the ITER Organization will be installing the first component of the machine in the basement of the Tokamak Building. The 10-met [...]

    Read more

Of Interest

See archived entries

760-metre dummy conductor fabricated at ASIPP

Wu Yu, Institute of Plasma Physics at the Chinese Academy of Science (ASIPP)

The conductor passing its acceptance test. (Click to view larger version...)
The conductor passing its acceptance test.
A big milestone was achieved on 2 October when the Institute of Plasma Physics at the Chinese Academy of Science (ASIPP) completed the assembly and testing of the first 760 metres of toroidal field dummy conductor.

This is a meaningful step for ITER China: now, according to the Procurement Arrangement, the conductor will be divided into two pieces. One hundred metres of the 760-metre-long conductor will be delivered to the European Domestic Agency and the remaining 660 metres will be delivered to the Japanese Domestic Agency where further testing will be performed for the coil manufacturing.
 
China will supply 7.51 percent of ITER's toroidal field conductors, whose procurement is shared by six Domestic Agencies. With the support of the Chinese Domestic Agency and the ITER Organization, ASIPP contracted with domestic enterprises and institutes to develop the related engineering work and technology. ASIPP established a quality management system; built three conductor assembly lines; and completed research, installation and commissioning of the manufacturing equipment. Three short samples (TFCN1, TFCN2, TFCN3) have all been tested in the Sultan test facility in Switzerland where they met ITER Organization requirements and passed the obligatory quality checks.

A team from the Chinese Domestic Agency, led by Director Luo Delong (centre), witnesses the welding of the dummy conductor. (Click to view larger version...)
A team from the Chinese Domestic Agency, led by Director Luo Delong (centre), witnesses the welding of the dummy conductor.
Conductor integrating began on 14 September with the section welding of the conduit, non-destructive examination, cable insertion, compaction, and spooling. At each stage—up to the final acceptance test—representatives from the Chinese Domestic Agency and the ITER Organization were present.

We would like to express our special thanks to colleagues at both of these institutions for all their support and the spirit of cooperation that they have demonstrated over these past five years. We hope to continue in that spirit.


return to the latest published articles