Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • A world in itself

    From a height of some 50 metres, you have the entire ITER worksite at your feet. The long rectangle of the Diagnostics Building stands out in the centre, with [...]

    Read more

  • US completes toroidal field deliveries for ITER

    The US Domestic Agency achieved a major milestone in February by completing the delivery of all US-supplied toroidal field conductor to the European toroidal fi [...]

    Read more

  • Thin diagnostic coils to be fitted into giant magnets

    Last week was marked by the first delivery of diagnostic components—Continuous External Rogowski (CER) coils—from the European Domestic Agency to the ITER Organ [...]

    Read more

  • Addressing the challenge of plasma disruptions

    Plasma disruptions are fast events in tokamak plasmas that lead to the complete loss of the thermal and magnetic energy stored in the plasma. The plasma control [...]

    Read more

  • Blending (almost) seamlessly into the landscape

    Located in the foothills of the French Pre-Alps, the ITER installation blends almost seamlessly into the landscape. The architects' choice ofmirror-like steel c [...]

    Read more

Of Interest

See archived articles

760 m dummy conductor fabricated at ASIPP

-Wu Yu, Institute of Plasma Physics at the Chinese Academy of Science (ASIPP)

The conductor passing its acceptance test. (Click to view larger version...)
The conductor passing its acceptance test.
A big milestone was achieved on 2 October when the Institute of Plasma Physics at the Chinese Academy of Science (ASIPP) completed the assembly and testing of the first 760 m Toroidal Field (TF) dummy conductor. This is a meaningful step for ITER China: now, according to the Procurement Arrangement, the conductor will be divided into two pieces. One hundred metres of the 760 metre-long conductor will be delivered to the European Domestic Agency and the remaining 660 m will be delivered to the Japanese Domestic Agency where further testing will be performed for the coil manufacturing.
 
China will supply 7.51 percent of ITER's Toroidal Field conductors, whose procurement is shared by six Domestic Agencies. With the support of the Chinese Domestic Agency and the ITER Organization, ASIPP contracted with domestic enterprises and institutes to develop the related engineering work and technology. ASIPP established a quality management system; built three conductor assembly lines; and completed research, installation and commissioning of the manufacturing equipment. Three TF short samples (TFCN1, TFCN2, TFCN3) have all been tested in the Sultan test facility in Switzerland where they met ITER Organization requirements and passed the obligatory quality checks.

A team from the Chinese Domestic Agency, led by Director Luo Delong (centre), witnesses the welding of the dummy conductor. (Click to view larger version...)
A team from the Chinese Domestic Agency, led by Director Luo Delong (centre), witnesses the welding of the dummy conductor.
Conductor integrating began on 14 September with the section welding of the conduit, non-destructive examination, cable insertion, compaction, and spooling. At each stage—up to the final acceptance test—representatives from the Chinese Domestic Agency and the ITER Organization were present. We would like to express our special thanks to colleagues at both of these institutions for all their support and the spirit of cooperation that they have demonstrated over these past five years. We hope to continue in that spirit.


return to the latest published articles