Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Links

Of Interest

See archived articles

Conferences


Management Advisory Committee meets in Barcelona

Following the request of the Eleventh ITER Council, MAC convened for a ''special'' session on schedule issues from 18-19 March in Barcelona chaired by Ranjay Sharan from India. (Click to view larger version...)
Following the request of the Eleventh ITER Council, MAC convened for a ''special'' session on schedule issues from 18-19 March in Barcelona chaired by Ranjay Sharan from India.
For the second time in its history, the ITER Council Management Advisory Committee (MAC) convened for an extraordinary session in order to assess the status of the ITER Project schedule and the implementation of corrective actions.

The meeting took place from 18-19 March at the headquarters of the European Domestic Agency in Barcelona in the attendance of high-level representatives of the ITER Organization and seven ITER Members.

Since the last special MAC meeting held in August 2012, the ITER Organization has worked closely with Domestic Agencies to complete the integration of Detailed Work Schedules (DWS)—detailed schedules that exist for every component or system. The ITER Organization and Domestic Agencies completed the integration of the remaining DWS, namely main vacuum vessel, ion cyclotron antenna, poloidal field coils and toroidal field structure, which will allow for monitoring of the schedule.

MAC requested that the Unique ITER Team continue to make significant efforts to take action focusing on super-critical milestones and to take all possible measures to keep to the Baseline schedule. The ITER Organization and Domestic Agencies are committed to doing their best to implement this request.