A team of engineering, science, and project management experts led by the US Department of Energy's (DOE) Office of Project Assessment visited the US ITER Project Office (USIPO) this week to assess the status and progress towards Critical Decision 2 (CD-2) for US hardware contributions.
The Lehman Review committee received briefings and reviewed documents from the USIPO. The committee noted several key achievements, including significant progress on recommendations from the last review in August 2010 and paid particular attention to prerequisites for achieving CD-2 status, scheduled for summer 2012. CD-2 is a critical decision that indicates US DOE approval of the project's performance baseline.
Ned Sauthoff, UISPO manager, observed, "This review is helpful for us to continue to learn and to improve. Since our last review, we've made significant headway in resolving design uncertainties and advancing design progress. We will continue to strengthen our team and processes as we move on toward CD-2."
Ed Synakowski, associate director for the Office of Fusion Energy Sciences at the DOE Office of Science, commented, "The USIPO is to be congratulated for their tremendous effort. The work you have done since the last review is obvious."