In December 2010, the Chinese Domestic Agency awarded the contract for the manufacture of ITER correction coils to ASIPP (Hefei, China), that had been closely involved in the construction of the EAST Tokamak in China and in R&D activities for ITER magnets. ASIPP is now actively preparing the installation of the manufacturing line for these coils in a dedicated building in Hefei. The selection process of all sub-suppliers should be completed by the end of this year.
During meetings in June between the ITER Organization, the Chinese Domestic Agency, ASIPP and sub-suppliers—the first in a series to monitor the qualification milestones at sub-suppliers—some of the key manufacturing options that are under development for the 18 correction coils and coil structures were highlighted.
"It is essential that our colleagues at the ASIPP and the Chinese Domestic Agency select the best manufacturing solution from the point of view of technical requirements, risk management and cost before launching the series production," says Arnaud.