Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Rendezvous | D and T to meet at JET in 2020

    In 2020, for the first time in more than 20 years, a reaction that only occurs in the core of the stars will be produced on Earth in a man-made machine. In the [...]

    Read more

  • On site | MOMENTUM believes in recent graduates

    It is rare for students to leave university and immediately begin work on a globally significant project. But thanks to the graduate program run by the project' [...]

    Read more

  • Tokamak Pit | Big steel elbow in place

    A cryostat feedthrough delivered by the Chinese Domestic Agency has become the first metal component of the machine to be installed in the Tokamak Pit, in an op [...]

    Read more

  • Neutral beam source | Europe awards EUR 20 million contract

    The contract, awarded to ALSYOM-SEIV (ALCEN group, France), launches the manufacturing phase for the beam source that will come on line in 2022 as part of the f [...]

    Read more

  • Image of the week | US Under Secretary of Science tours site

    Five months, almost to the day, after the US Secretary of Energy Rick Perry visited ITER, his deputy, Under Secretary for Science Paul Dabbar, stood by the same [...]

    Read more

Of Interest

See archived entries

Worksite postcards

Since the last concrete pour of the Tokamak Complex basemat slab two months ago, the ITER worksite has been undergoing a transformation as the consortium responsible for foundation works (GTM) has been winding down its activities and the consortium charged with the construction of the Tokamak Complex and eight auxiliary buildings (VFR) has taken possession of the different work areas.

 (Click to view larger version...)
In this picture taken on 30 October, the tallest crane on site (left, 82 m) is being used to carefully position the boom of the 52-metre crane at the very centre of the basemat. Work is also underway on a third crane (far right, in red); the concrete base is in place (5 x 5 m) and the metal structure is rising section by section.

 (Click to view larger version...)
Forming a perfect circle around the central crane are the starter bars for the 3.25-metre-thick bioshield wall that will surround the machine. A wider circle, with starter bars spaced at regular intervals, marks out the columns that will support the second slab level (B1) of the Tokamak Complex.

 (Click to view larger version...)
Noticeable change is also taking place on the site of the Assembly Building, to the south of the Seismic Pit. In this picture Yves Belpomo, construction coordinator for ITER Building Site & Infrastructure, and Vincenzo Sarica, head controller for concrete and steel structures at Engage (architect/engineer for the European Domestic Agency), are seen inspecting one of the 12-metre column sections that will be assembled as part of the steel "skeleton" of the Assembly Building.

 (Click to view larger version...)
Eleven 60-metre pillars will be spaced every 9.3 metres along each side of the basemat to support the steel frame and the roof of the building. A parallel row of columns—not quite as thick and set inwards by a few metres—will support the rails for the double 750-tonne gantry crane and the two 50-tonne auxiliary cranes.

Bolting the bracings that tie the two parallel rows of columns together is not a simple operation: first, the bolts are tightened to 75 percent of the nominal torque; the final torque is applied only after strict control of the assembly's geometry.


return to the latest published articles