Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cooling water system | The tanks within a tank

    Deep inside the bowels of the Tokamak Building, the entrance to one of most spectacular rooms of the whole installation resembles that of a broom cupboard. [...]

    Read more

  • ITER assembly | Last major assembly contract signed

    One year after finalizing two major machine assembly contracts, the ITER Organization has chosen the contractors who will carry out assembly and installation ac [...]

    Read more

  • ITER Science | The towering importance of data

    The most important product of ITER is data, which will be used to produce the information needed to build models for DEMO and commercial reactors—and much more. [...]

    Read more

  • Image of the week | In my arms!

    In late November, one part of the 'shell' that encloses every vacuum vessel sector—a right-hand outboard thermal shield panel—had been mounted on a giant pre-as [...]

    Read more

  • Brexit | The UK will remain part of ITER

    'It was a great Christmas present,' says Ian Chapman, head of the United Kingdom Atomic Energy Authority. Many in the ITER community would agree. The Brexit neg [...]

    Read more

Of Interest

See archived entries

Worksite postcards

Since the last concrete pour of the Tokamak Complex basemat slab two months ago, the ITER worksite has been undergoing a transformation as the consortium responsible for foundation works (GTM) has been winding down its activities and the consortium charged with the construction of the Tokamak Complex and eight auxiliary buildings (VFR) has taken possession of the different work areas.

 (Click to view larger version...)
In this picture taken on 30 October, the tallest crane on site (left, 82 m) is being used to carefully position the boom of the 52-metre crane at the very centre of the basemat. Work is also underway on a third crane (far right, in red); the concrete base is in place (5 x 5 m) and the metal structure is rising section by section.

 (Click to view larger version...)
Forming a perfect circle around the central crane are the starter bars for the 3.25-metre-thick bioshield wall that will surround the machine. A wider circle, with starter bars spaced at regular intervals, marks out the columns that will support the second slab level (B1) of the Tokamak Complex.

 (Click to view larger version...)
Noticeable change is also taking place on the site of the Assembly Building, to the south of the Seismic Pit. In this picture Yves Belpomo, construction coordinator for ITER Building Site & Infrastructure, and Vincenzo Sarica, head controller for concrete and steel structures at Engage (architect/engineer for the European Domestic Agency), are seen inspecting one of the 12-metre column sections that will be assembled as part of the steel "skeleton" of the Assembly Building.

 (Click to view larger version...)
Eleven 60-metre pillars will be spaced every 9.3 metres along each side of the basemat to support the steel frame and the roof of the building. A parallel row of columns—not quite as thick and set inwards by a few metres—will support the rails for the double 750-tonne gantry crane and the two 50-tonne auxiliary cranes.

Bolting the bracings that tie the two parallel rows of columns together is not a simple operation: first, the bolts are tightened to 75 percent of the nominal torque; the final torque is applied only after strict control of the assembly's geometry.


return to the latest published articles