Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Question of the week | Will fusion run out of fuel?

    One of the paradoxes of fusion, the virtually inexhaustible energy of the future, is that it relies on an element that does not exist—or just barely. Tritium, o [...]

    Read more

  • Managing data | Setting up a robust process

    Are the ITER systems and processes robust enough to manage the technical and project data for a program of ITER's complexity? Will quality information be made a [...]

    Read more

  • Image of the week | Bullseye

    Two perfectly circular structures, looking a lot like archery targets, have been installed on the west-facing wall of the Tokamak Complex. They are not for sh [...]

    Read more

  • Art and science | Seeking new perspectives on fusion

    Standing in the middle of the Tokamak Building, sound artist Julian Weaver positions his 3D microphone near one of the openings of the bioshield to record the s [...]

    Read more

  • Worksite photos | The view one never tires of

    For the past three-and a half years, ITER Communication has been documenting construction progress from the top of the tallest crane on the ITER worksite. Altho [...]

    Read more

Of Interest

See archived entries

Component transport

Roll on to the new ramp!

R.A.

A new roll-on/roll-off ramp will facilitate the transhipment of components in Fos harbour.

Since early 2015, the seven ITER Members have been shipping components to ITER. The largest of these—called highly exceptional loads—can weigh up to 600 tonnes and require sophisticated logistics and robust infrastructures to transport and manoeuvre.

The new infrastructure was designed to simplify and secure the transhipment sequences between the onloading of components from the sea-going ship and the land journey to the ITER site. Here, the four rectifier-transformers from China are being loaded into the new barge ''Beluga 2'' to be transported across the inland sea Etang-de-Berre. (Photo DAHER) (Click to view larger version...)
The new infrastructure was designed to simplify and secure the transhipment sequences between the onloading of components from the sea-going ship and the land journey to the ITER site. Here, the four rectifier-transformers from China are being loaded into the new barge ''Beluga 2'' to be transported across the inland sea Etang-de-Berre. (Photo DAHER)
When they reach the industrial harbour at Fos-sur-Mer (Marseille, southern France) the journey is far from over. A sequence of delicate operations still needs to be performed before the components can be transported over three to five nights to the ITER site, which is situated some 100 kilometres to the northeast.

This phase, which is essentially a transfer from sea-going vessel to land transporter, is by far the most challenging, as the more handling a component is subjected to the longer the time spent and the higher the cost and risk.

In order to simplify, secure and focus the transhipment sequences, new equipment has recently been added to the existing harbour infrastructure in Fos-sur-Mer.

A milestone in France's committment to ITER

The new RO-RO ramp is a EUR 2.7 million investment jointly financed by Agence Iter-France, the agency that acts as interface between ITER and its host country (85 percent of the total cost); the cargo handling company Sosersid; the barge operator CFT; and ITER global logistics provider DAHER. "This equipment is an important milestone in France's commitment to the ITER Project," said Jacques Veyron, the director of Agence Iter France.

The roll-on/roll-off ("RO-RO") ramp that was inaugurated on 20 September eliminates the need for vertical handling once the component has been unloaded from the ship. Although the ramp will be accessible for other uses, priority is given to the ITER loads when they come in.

Approximately 18 metres long and 30 metres large, the new RO-RO ramp is the largest of its kind in France. Representing an investment of EUR 2.7 million, it can accommodate combined loads (components and trailers) of up to 880 tonnes.

Four rectifier-transformers shipped by ITER China, each weighing close to 130 tonnes, were the first to use the ramp on their way to ITER last week (read related article).

In the six years to come, the ramp will accommodate approximately 200 highly exceptional loads (HELs)—among them the first toroidal field coil and the first vacuum vessel sector, both expected at the end of 2018.



return to the latest published articles