Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • In-vessel electrical systems | What it takes to wire up a fusion reactor

    While the challenges of keeping cables operational in harsh environments such as jet engines and nuclear fission reactors have been understood for a long time, [...]

    Read more

  • Assembly preparation | Off goes the lid

    In the summer of 2017, a circular platform was installed inside of the large steel-and-concrete cylinder of the Tokamak pit. The 200-tonne structure was meant t [...]

    Read more

  • Deliveries | Two coils on their way

    For the past five years, 'highly exceptional loads' (HEL) have been successfully travelling along the ITER Itinerary to be delivered to the ITER site. As the pr [...]

    Read more

  • ITER NOW video | Ready for the big lifts

    This new video in our "ITER NOW" series provides an insider's view of the recent load tests performed as the ITER Organization prepares for the machin [...]

    Read more

  • Divertor | Far more than a fancy ashtray

    It has been likened to the filter of a swimming pool or an oversized ashtray. It has been called alien in shape and hellish in its affinity for heat. But whatev [...]

    Read more

Of Interest

See archived entries

First toroidal field coil structure

Submillimetric tolerances achieved

ITER Japan

In major news for the ITER superconducting magnet program, the first toroidal field coil case has passed all fitting tests. The two sides of the huge component—as tall as a four-storey building and machined from 20-centimetre-thick steel—were matched within gap tolerances of 0.25 mm to 0.75 mm, an accuracy of more than one order of magnitude in relation to conventional high-precision welded structures of comparable size.

Toroidal field cases are D-shaped components, with the inboard leg (right) corresponding to the straight-backed portion of the letter and the outboard leg (left) corresponding to the rounded portion. The two legs were successfully matched in fitting tests at Hyundai Heavy Industries in December. (Click to view larger version...)
Toroidal field cases are D-shaped components, with the inboard leg (right) corresponding to the straight-backed portion of the letter and the outboard leg (left) corresponding to the rounded portion. The two legs were successfully matched in fitting tests at Hyundai Heavy Industries in December.
On 18 and 19 December 2017, precision laser trackers were used to measure the alignment of inboard and outboard legs of the first toroidal field coil case as well as the precise position and orientation of the heavy steel segments. The measurement results were sent electronically to the ITER Organization for detailed analysis, where it was confirmed that giant steel structures matched at all welding grooves with gaps ranging from 0.25 mm to 0.75 mm, fully respecting specified tolerances.

"This is a technological achievement of the highest order," declared Eisuke Tada, ITER Deputy Director-General, as he attended a ceremony on 26 December at the testing site. "A component that is 16 metres in height, weighing 190 tonnes, has been successfully pre-assembled to within sub-millimetre tolerances by multiple manufacturers. The international nature of this achievement makes it all the more remarkable."

The toroidal field coils cases provide protective covers for the toroidal field winding packs, the superconducting core of the magnets wound from approximately 5.5 kilometres of niobium-tin conductor. The thick steel cases also have a structural role to play, anchoring the poloidal field coils, the central solenoid and the correction coils and withstanding huge electromagnetic loads inside the machine.

Japan* is responsible for producing 19 toroidal field coil structures (for ITER's 18 toroidal field coils plus one spare). Nine of the structures will encase the toroidal field coil winding packs produced in Japan, while ten—including this first unit—will be shipped to Italy for the insertion of winding packs produced in Europe.

The inboard leg of the first coil case was manufactured at Mitsubishi Heavy Industries, Ltd. (Kobe, Japan). During fitting tests in July 2017 the two sections of the inboard leg—the U-shaped sub-assembly ("AU") that will contain the superconducting core plus a cover plate ("AP")—were successfully paired with gap tolerances of 0.25 mm to 0.75 along the entire 14-metre-long weld groove.

At Hyundai Heavy Industries in Ulsan, Korea, the outboard leg sub-assemblies were first fitted together to verify manufacturing precision. Then the principal segments of the coil case, manufactured in both Korea and Japan were positioned and measured. (Click to view larger version...)
At Hyundai Heavy Industries in Ulsan, Korea, the outboard leg sub-assemblies were first fitted together to verify manufacturing precision. Then the principal segments of the coil case, manufactured in both Korea and Japan were positioned and measured.
The outboard leg was contracted by Japan to Hyundai Heavy Industries in Ulsan, Korea. The ultimate test was then to verify that structures manufactured in two locations following stringent ITER Organization specifications would fit together perfectly. "Ultimately, the story of the toroidal field coil cases is the occasion to showcase the spirit that underlies the ITER Project in its entirety—the "One-ITER" spirit of teamwork that unites us around one design, one schedule and one mission," stressed Deputy Director-General Tada.

At Hyundai, the outboard leg sub-assemblies ("BU" and "BP") were first fitted together to verify manufacturing precision. Then, on 18 and 19 December the principal segments of the coil case ("AU," manufactured in Japan and shipped to Korea, and "BU" manufactured in Korea) were positioned and measured. (Please see the photo gallery below for further explanations.)

The required tolerances of bevels at the welding grooves were respected across the board at less than 1 millimetre—with gap variations ranging from 0.25 mm to 0.75 mm. Witnesses on hand during the fitting tests included representatives of the ITER Organization, the Japanese and Korean Domestic Agencies, the European Domestic Agency (which will be receiving the component), and manufacturers Mitsubishi Heavy Industries and Hyundai Heavy Industries.

The successful fitting trials of the first toroidal field coil case demonstrates that the final assembly—the insertion of the superconducting winding pack followed by closure welding—can be achieved within the tight tolerances required. This is excellent news, as work proceeds on the fabrication and precision machining of elements for the other 18 cases.

The first case is now on its way to SIMIC (Italy), where the first European winding pack has been delivered for insertion.

*QST—Japan's National Institutes for Quantum and Radiological Science and Technology—is responsible for the procurement of all components allocated to Japan by the ITER Organization.



return to the latest published articles