Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Fusion world | ORNL researchers excited to be part of history at JET

    As part of a long-running collaboration, the US Oak Ridge National Laboratory is supporting landmark experiments aiming for a fusion milestone at JET. This summ [...]

    Read more

  • Portfolio | It's happening in the pit

    There has always been something breathtaking about the vast cylindrical volume that will accommodate the ITER Tokamak. When it was empty, it felt like a high-te [...]

    Read more

  • Image of the week | First weld for the top lid

    Of the four sections that make up the ITER cryostat, the top lid is the thickest, second heaviest (more than 700 tonnes) and most structurally complex. On Monda [...]

    Read more

  • Vacuum vessel welding | Contract awarded to Spanish company

    The ITER Organization has concluded a contract with the Spanish company ENSA (Equipos Nucleares SA) for the welding of the ITER vacuum vessel. ENSA is no stran [...]

    Read more

  • Spherical tokamak | MAST's divertor concept yields positive results

    During the first months of experimentation on the MAST Upgrade tokamak in the United Kingdom, an innovative plasma exhaust concept has demonstrated positive res [...]

    Read more

Of Interest

See archived entries

Image of the week

More than meets the eye

Eight months separate these two satellite-like images of the ITER site.

 (Click to view larger version...)
In July 2019, nine years into construction, concrete pouring had reached the seventh and  final level (L5) in the Tokamak Building but the edifice was still roofless—the first pillar of the steel structure would only be installed in September. Eight months later, the roof is completed, and so is the first layer of cladding on the three sides of the building.

 (Click to view larger version...)
To the left, in the July 2019 image, the cooling cells in the heat rejection zone are still under construction and piping and pumps are not yet installed.

Adjacent to the heat rejection zone, the batching plant is still active, producing the last of the 250,000 cubic metres of concrete that were needed for building construction. Now that 75 percent of civil works to First Plasma is complete, the volume of concrete needed is only a fraction of what it used to be. The batching plant has been dismantled and the production of a local facility in nearby Vinon-sur-Verdon will be sufficient to cover present and future needs.

In terms of worksite progress there is, however, more than just meets the eye: in July 2019, when ITER and its Indian partners celebrated the finalization of both the cryostat base and lower cylinder, the upper cylinder was in the early stages of assembly and welding. Last month, workers were busy cleaning the finalized upper cylinder prior to wrapping it into its protective cocoon.

Assembly preparations are accelerating. In July 2019, the different parts of the upending tool, manufactured in Korea, had not yet taken to the sea. Now, the fully assembled tool is being maneuvered and tested. And in every building, unseen by the peering eye of the drone hovering above the platform, equipment installation is progressing quickly, bringing ITER closer to its first major appointment with history—the production of First Plasma in less than six years.


return to the latest published articles