Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Image of the week

More than meets the eye

Eight months separate these two satellite-like images of the ITER site.

 (Click to view larger version...)
In July 2019, nine years into construction, concrete pouring had reached the seventh and  final level (L5) in the Tokamak Building but the edifice was still roofless—the first pillar of the steel structure would only be installed in September. Eight months later, the roof is completed, and so is the first layer of cladding on the three sides of the building.

 (Click to view larger version...)
To the left, in the July 2019 image, the cooling cells in the heat rejection zone are still under construction and piping and pumps are not yet installed.

Adjacent to the heat rejection zone, the batching plant is still active, producing the last of the 250,000 cubic metres of concrete that were needed for building construction. Now that 75 percent of civil works to First Plasma is complete, the volume of concrete needed is only a fraction of what it used to be. The batching plant has been dismantled and the production of a local facility in nearby Vinon-sur-Verdon will be sufficient to cover present and future needs.

In terms of worksite progress there is, however, more than just meets the eye: in July 2019, when ITER and its Indian partners celebrated the finalization of both the cryostat base and lower cylinder, the upper cylinder was in the early stages of assembly and welding. Last month, workers were busy cleaning the finalized upper cylinder prior to wrapping it into its protective cocoon.

Assembly preparations are accelerating. In July 2019, the different parts of the upending tool, manufactured in Korea, had not yet taken to the sea. Now, the fully assembled tool is being maneuvered and tested. And in every building, unseen by the peering eye of the drone hovering above the platform, equipment installation is progressing quickly, bringing ITER closer to its first major appointment with history—the production of First Plasma in less than six years.


return to the latest published articles