Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Mitigating plasma disruptions | Second IAEA Technical Meeting held at ITER

    Disruptions of tokamak plasmas (fast events leading to the complete loss of thermal and magnetic energy on millisecond timescales) can pose significant risks to [...]

    Read more

  • On site | Distinguished visitors from Korea

    Participants to the Europe-Korea Conference on Science and Technology (EKC) in Marseille took an afternoon off, last week, to pay a visit to the ITER site. The [...]

    Read more

  • Image of the week | In the slow cooker

    The thermostat is set at 140 °C and the timer on 72 hours. But contrary to the roasting of a Thanksgiving Turkey, the 'curing' of the resin inside a poloidal fi [...]

    Read more

  • Fusion world | "It just isn't like any other kind of research..."

    On 21 April 1956, a fleet of large black limousines travelled in convoy from London to Harwell, just south of Oxford, to make an extraordinary and historic visi [...]

    Read more

  • Facility operation | Preparing ~100 System Concepts of Operation

    System Concepts of Operation (ConOps) documents are used at ITER—and at other science and engineering projects—to provide information on the operation and use o [...]

    Read more

Of Interest

See archived entries

Council milestone #50

The way to assembly is open

Passing an ITER Council milestone is always an achievement. Passing this milestone at this moment is much more than that: it is a demonstration that, despite the constraints imposed by the public health context, the ITER Organization, the European Domestic Agency and their contractors are determined to keep moving forward and to remain on schedule.

Totalling approximately 1,000 tonnes, the loads are ready to undertake their 170-metre-long journey from the entrance of the Assembly Hall all the way to the opposite end of the newly created crane hall. (Click to view larger version...)
Totalling approximately 1,000 tonnes, the loads are ready to undertake their 170-metre-long journey from the entrance of the Assembly Hall all the way to the opposite end of the newly created crane hall.
ITER Council milestone #50, which was successfully achieved two days ahead of schedule late on 28 March, is of considerable significance for the project, as it opens the way for the launch of the machine assembly phase.

The milestone consisted in demonstrating that the heavy lift cranes could successfully travel between the Assembly Hall and the Tokamak Building in order to deliver components to the Tokamak pit.

Three actions were required: first, the completion of the crane hall structure; second, the removal of the temporary wall  separating the buildings; and finally, the verification of the overhead crane load path in the Tokamak Building.

The last operation, both spectacular and delicate, required validating the full 170-metre-long runway of the double bridge crane—from the entrance of the Assembly Hall, all the way to the opposite end of the newly created crane hall and back.

It was a display of Titans, with no less than 1,000 tonnes of steel and concrete test loads attached to the giant hoists of the bridge crane (more details in the image gallery below).

The main load has just passed the protruding lid that closes the assembly pit. The full theatre of future assembly operations is fully visible ... (Click to view larger version...)
The main load has just passed the protruding lid that closes the assembly pit. The full theatre of future assembly operations is fully visible ...
Initiated at 8:00 a.m., the operation lasted well into the night and was only considered completed when the crane and its loads had returned to the Assembly Hall and were secured. By then Saturday had turned into Sunday, but 31 March—the official target for ITER Council milestone #50*—was still 48 hours away.

The crane and its loads moved slowly, taking long pauses at strategic locations: at the "seismic link" between the two buildings, at the threshold of the Tokamak Building, over the protruding lid of the Assembly Pit ...

All the while, metrology systems were monitoring the deflections that the loads were causing to the runway beams and steel pillars—essential information for validating the crane hall's structure and achieving the milestone.

With the temporary wall between the Assembly Hall and Tokamak Building removed, one could take in, for the first time, the full theatre of future assembly operations—a huge open space that even dwarfs the 20-metre-high vacuum vessel sector sub-assembly tools.

It was an awesome view that conveyed the unique size, complexity and beauty of ITER.

* Since early 2016, the ITER Organization has been tracking project progress against high-level milestones agreed by the ITER Council. Whether related to construction, manufacturing or deliveries—or rather to programmatic milestones like recruitment and contract signatures—these milestones are underpinned in the schedule by the many thousands of activities that make up progress to First Plasma.

See the Fusion for Energy website for a related article.
 

 