Toroidal field coils | Finishing touches on site

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryodistribution | Blowing cold and hot

    If the cryodistribution system were a railroad, the cryogenic termination cold box would be its main switch. A massive structure packed with pipes, valves, elec [...]

    Read more

  • Pre-assembly activities | Captured from on high

    With assembly tools standing 22 metres tall, massive bridge cranes straddling the width of the building, and alien-shaped components placed at regular intervals [...]

    Read more

  • 27th ITER Council | Assembly moves ahead

    The Twenty-Seventh Meeting of the ITER Council took place by videoconference on 18 and 19 November 2020, chaired by LUO Delong from China. Representat [...]

    Read more

  • Fusion world | Translating JET into ITER

    With an inner wall made of beryllium and tungsten, the European tokamak JET is the only tokamak in the world to share the same material environment as ITER. Whe [...]

    Read more

  • Worksite | Major progress you don't see from the air

    There was a time when aerial pictures of the ITER worksite taken at six-month intervals showed spectacular change. Buildings and structures sprouted from previo [...]

    Read more

Of Interest

See archived entries

Toroidal field coils

Finishing touches on site

Between the time a toroidal field coil is delivered to ITER and the moment it is ready to enter the pre-assembly process, certain tasks must be performed: the welds in the helium piping need to be leak-tested and additional handling and pre-assembly equipment must be added.

Delivered on 17 April, TF9 from Europe is now stored in a dedicated building, where tests are being performed and handling and pre-assembly equipment is being installed. (Click to view larger version...)
Delivered on 17 April, TF9 from Europe is now stored in a dedicated building, where tests are being performed and handling and pre-assembly equipment is being installed.
Two toroidal field coils, TF9 from Europe and TF12 from Japan, were recently delivered to ITER. A third coil, TF13, sailed from Kobe harbour in Japan on 15 May 2020 and is expected reach France in mid-June.

Temporarily alone in the Cryostat Workshop, TF12 from Japan was recently extracted from its transport frame. (Click to view larger version...)
Temporarily alone in the Cryostat Workshop, TF12 from Japan was recently extracted from its transport frame.
On each component, preparatory work must be accomplished before the coils are transferred to the upending tool in the Assembly Hall to be lifted to vertical and installed on the wings of the sub-sector assembly tools.

TF13, which will be paired with TF12 in the first ''pre-assembly,'' sailed from Kobe harbour in Japan on 15 May 2020 and is expected reach France in mid-June. (Click to view larger version...)
TF13, which will be paired with TF12 in the first ''pre-assembly,'' sailed from Kobe harbour in Japan on 15 May 2020 and is expected reach France in mid-June.
The first toroidal field coil "pair"—TF12 and TF13—will be associated with vacuum vessel sector # 6 (which Korea recently finalized) and thermal shield panels to form the first of nine "sector sub-assemblies" to be descended into the Tokamak assembly pit.


return to the latest published articles