Toroidal field coils
Finishing touches on site
2 Jun 2020
Between the time a toroidal field coil is delivered to ITER and the moment it is ready to enter the pre-assembly process, certain tasks must be performed: the welds in the helium piping need to be leak-tested and additional handling and pre-assembly equipment must be added.
On each component, preparatory work must be accomplished before the coils are transferred to the upending tool in the Assembly Hall to be lifted to vertical and installed on the wings of the sub-sector assembly tools.
The first toroidal field coil "pair"—TF12 and TF13—will be associated with vacuum vessel sector # 6 (which Korea recently finalized) and thermal shield panels to form the first of nine "sector sub-assemblies" to be descended into the Tokamak assembly pit.