Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Remembering Bernard Bigot, ITER Director-General 2015-2022

    On the ITER site, the machinery of construction was humming just like on any weekday. Workers were concentrating on their tasks, laying rebar for new buildings [...]

    Read more

  • Tokamak assembly | Preparing for the Big Lift

    The distance was short but the challenge daunting: on Thursday last week, the first section of the plasma chamber was lifted 50 centimetres above its suppor [...]

    Read more

  • Image of the week | 13th toroidal field coil arrives from Europe

    The toroidal field coil procurement effort has been one of the longest of the ITER program, initiated by Procurement Arrangements signed in 2007 and 2008. Manuf [...]

    Read more

  • Diagnostics | Final Procurement Arrangement signed

    ITER Diagnostics reached an important milestone in December 2021 when it concluded the last Procurement Arrangement of the diagnostics program. After signing a [...]

    Read more

  • On site | A quick visit to the Control Building

    Work is progressing on the ITER Control Building, ergonomically designed for the 60 to 80 operators, engineers and researchers who will call it home.  [...]

    Read more

Of Interest

See archived entries

Pre-assembly

Prepping the first coil pair

Since their delivery to ITER, in April and July of last year, toroidal field coils #12 and #13 from Japan have been slowly and steadily gaining weight. As the 320-tonne components are prepped for pre-assembly, close to 10 tonnes of equipment, some of it temporary, are being added to their already considerable mass.

In a vast storage/workshop facility on site, a pair of Japanese toroidal field coils is being prepped for the first pre-assembly operation on the sector sub-assembly tools. The process adds approximately 10 tonnes of equipment, some of it temporary, to their already considerable mass. (Click to view larger version...)
In a vast storage/workshop facility on site, a pair of Japanese toroidal field coils is being prepped for the first pre-assembly operation on the sector sub-assembly tools. The process adds approximately 10 tonnes of equipment, some of it temporary, to their already considerable mass.
"Some of the equipment is added at ITER because it is too fragile to be exposed to the long sea journey, or because it depends on the reverse engineering assessment carried out after arrival to match the coil with neighbouring components," explains Sebastien Koczorowski, the responsible officer for the toroidal field coil preparation activities. "Other equipment—like the interface clamps or the inter-coil structures—need to be installed and customized on site."

The largest part of the added weight, however, consists of equipment necessary for the lifting and subsequent installation of the coils on pre-assembly tooling in the Assembly Hall—for example a set of massive lifting lugs required for transport by the overhead cranes, or components that will interface with the giant sector sub-assembly tool.

Standing on the scaffolding or crouching under the coils, several teams are at work. Members of the DYNAMIC SNC consortium (one of two machine assembly contractors) they are busy installing the delicate network of the external cooling circuit (130 metres of thin piping), connecting the low-voltage wires for the diagnostics systems, or match-drilling for various interface elements.

It will take another few months to finalize the equipment work and transfer the coils to the sector sub-assembly tool. Once associated to vacuum vessel sector #6 and corresponding thermal shield panels, they will form the first of the nine pre-assemblies required for the ITER Tokamak.

In the vast storage/workshop facility, a second pair of coils will soon undergo a similar preparation process, which will be repeated until all nine pre-assemblies are complete and the machine torus finalized.



return to the latest published articles