News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Toroidal field coils

Eight now on site

With eight D-shaped magnet coils on site and two travelling, the project has officially passed the halfway mark in the procurement of 19 toroidal field coils.

Toroidal field coil #6 (TF6) arrives at ITER before dawn on 3 September 2021. (Click to view larger version...)
Toroidal field coil #6 (TF6) arrives at ITER before dawn on 3 September 2021.
Eighteen toroidal field coils, placed vertically around the ITER plasma chamber, will produce the magnetic field that will confine the plasma particles; a nineteenth will be supplied to the project as a spare.

The coils will be associated by pair with each vacuum vessel sector. Two tools have been erected in the ITER Assembly Hall for this sub-assembly activity, and the first operation is underway on vacuum vessel sector #6.

From niobium-tin conductor supplied by ITER Members China, Europe, Japan, Korea, Russia and the United States, two procuring agencies—the Domestic Agencies of Europe and Japan—are carrying out the complex winding and casing tasks necessary to delivering the final coils. 

On Friday 3 September, the European agency Fusion for Energy delivered TF6—the eighth coil to arrive on site. To date, five coils have been delivered by Europe and three from Japan; another two Japanese coils are travelling toward ITER now.

One of ITER's longest-lead procurement programs has reached the halfway mark in terms of deliveries.



return to the latest published articles