Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryoplant | First steps toward commissioning

    Every week since the beginning of November, a tube trailer filled with approximately 4,600 cubic metres (750 kg) of compressed gaseous helium delivers its load [...]

    Read more

  • Training | Seeking the next group of Monaco-ITER Fellows

    Recruitment opens for the next Monaco-ITER Postdoctoral Fellowship campaign on 17 January 2022. If your PhD was awarded after 1 January 2019—or you are about to [...]

    Read more

  • Contemporary art | Venet's "arcs" are as heavy as ITER coils

    A 'conceptual artist' among the most prominent on the art scene today, Bernar Venet is not impressed by massive towering steel structures like those in the ITER [...]

    Read more

  • Image of the week | Final activities on Europe's first sector

    The first vacuum vessel sector produced in Europe will arrive at ITER next year. Five of ITER's nine vacuum vessel sectors are the responsibility of Europe's AM [...]

    Read more

  • Vacuum vessel sector preparation | Lessons learned reduce work time by half

    In life as in the assembly of the ITER machine, 'lessons learned' are what makes progress possible. Gains in wisdom, time, skill, investment can be incremental; [...]

    Read more

Of Interest

See archived entries

Central solenoid module

Tests and verifications prior to assembly

In January next year, the "most powerful magnet in the world" will begin taking shape. The first module of the Tokamak's central solenoid will be positioned on a bespoke platform and the assembly process will begin in the ITER Assembly Hall. One by one, the six modules that make up the 18-metre tall, 1,000-tonne component will be stacked one upon the other and held together by a sets of tie plates (18 exterior and 9 interior).

Delivered to ITER in September, the first central solenoid module is undergoing a battery of tests and verifications—metrology, sensors, electrical insulation inspection, etc. Assembly of the 18-metre tall, 1,000-tonne central solenoid is set to begin in January 2022. (Click to view larger version...)
Delivered to ITER in September, the first central solenoid module is undergoing a battery of tests and verifications—metrology, sensors, electrical insulation inspection, etc. Assembly of the 18-metre tall, 1,000-tonne central solenoid is set to begin in January 2022.
At both ends, the tie plates will be locked to "key blocks" weighing up to 6 tonnes each. Removable hydraulic jacks inside the key blocks will exert huge pressure (210 meganewtons¹) on the module stack and keep them in mechanical compression.

This huge load is indispensable in order for the central solenoid to withstand the mechanical and magnetic forces it will be submitted to. These forces are equivalent to twice the thrust of a space shuttle...

Two central solenoid modules have already been delivered to ITER. The first one is presently undergoing a battery of tests and verifications—metrology, sensors and electrical insulation inspection, etc.

The remaining five modules (including one spare) are in the final stages of fabrication at General Atomics in California. All are expected to be delivered by mid-2023.

¹A meganewton (MN) is a unit of force corresponding to the force required to accelerate a mass of one million kilograms by one metre per second.



return to the latest published articles