Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • On site | 28 who "truly shined"

    The new ITER Star Awards recognize exemplary performance and commitment. Every year, during the annual assessment campaign, ITER staff may be recognized for exe [...]

    Read more

  • MT-28 Conference | Superconducting magnets as a catalyst

    Many passers-by paused for a moment and picked up their cell phones to capture the scene. It was indeed rare to see dancers on the square outside of the Pavillo [...]

    Read more

  • Fusion world | TCV tokamak turns 30

    The Swiss TCV tokamak (for Tokamak à Configuration Variable, or 'variable configuration' tokamak) has been exploring the physics of nuclear fusion for 30 years [...]

    Read more

  • Image of the week | Port cell with a view

    A visit to ITER would not be complete without a peek into the Tokamak pit where the machine is being progressively assembled. For several years, one of the equa [...]

    Read more

  • Visit | Chinese Minister reaffirms "full support"

    ITER Director-General Pietro Barabaschi and the Chinese Minister of Science and Technology (MOST) Wang Zhigang share a common academic background. They both tra [...]

    Read more

Of Interest

See archived entries

Vacuum vessel sector preparation

Lessons learned reduce work time by half

In life as in the assembly of the ITER machine, "lessons learned" are what makes progress possible. Gains in wisdom, time, skill, investment can be incremental; they can also be spectacular. The ongoing preparation works on the second vacuum vessel sector, Sector #1(7), offer a striking example of the benefits that come with experience: whereas it took 36 work weeks to fit the first sector with sensors, cables and flux loops, it is expected that the same operations on the second sector will only require 15 to 17 work weeks—less than half the time.

Whereas it took 36 work weeks to fit the first sector with sensors, cables and flux loops, it is expected that the same operations on the second sector will only require 15 to 17. (Click to view larger version...)
Whereas it took 36 work weeks to fit the first sector with sensors, cables and flux loops, it is expected that the same operations on the second sector will only require 15 to 17.
Although the packaging of both sectors for shipment from Korea was similar, the duration of the unpacking operations was divided by two the second time around. "We knew from experience where to expect difficulties and we were able to anticipate and adapt," says Alex Martin, the head of the ITER Vacuum Vessel Section.

Once extracted from its transportation frame, cabin-sized metal box and multi-layered wrapping, the first vacuum vessel sector, Sector #6, had been subjected to a helium leak test. No leaks above the limit of detection were found and the values obtained were two orders of magnitude tighter than the acceptance criteria.

"We had full demonstration of the quality control procedures performed by the manufacturer, Hyundai Heavy Industries, and ITER Korea. So we decided that, as far as Sector #1(7) was concerned, we would do without the on-site leak test," says Martin. And thus the teams saved another week.

With fewer bosses but more clips to install, the amount of work to equip the second sector is equivalent to the first. But this time, the organization is different. "We've gone from a sequential to a parallel approach. Sector #6 kept us busy for approximately four months on this task; this time, with the optimization of the processes, we expect to complete the works in two months."

As equipment work on Sector #1(7) is nearing completion, preparation for moving the component into the upending tool and then into the sector sub-assembly tool (SSAT-1), has already started. "If we compare with the first vacuum vessel sector, we are now ten weeks ahead overall and we are already working on the lift operation, preparing for the installation of the radial beam and the sector lifting tool."

During the sub-assembly operation, Sector #1(7) will be joined with toroidal field coils #8 (TF8 from Japan) and #9 (TF9 from Europe). This second sub-assembly—which will certainly also benefit from lessons learned on the first operation—is scheduled to be lowered into the Tokamak pit by mid-2022.

With another seven vacuum vessel sectors to equip prior to assembly and installation, is there still room for progress and additional gains in time? "Always," smiles Alex Martin.



return to the latest published articles