  • Portfolio | Sector repair has started

    Built up against vacuum vessel sector #7, the scaffolding reaches almost 20 metres in height and masks the massive component. Streaks of blinding light, filtere [...]

    Read more

  • Fusion world | Public/private consortium is building the DTT tokamak

    The Divertor Test Tokamak in Italy is creating a new model for engagement with industry in fusion research. ITER helped to pave the way. The Divertor Test Tokam [...]

    Read more

  • Image of the week | An architectural paradox

    There is something deliberately paradoxical in the architectural treatment of the ITER buildings. On the one hand, the alternation between the mirror-like stai [...]

    Read more

  • Former French Prime Minister | A fan then and now

    For Jean-Pierre Raffarin, former Prime Minister of France (2002-2005) who visited ITER on Friday 15 March, touring the ITER installation with ITER Director-Gene [...]

    Read more

  • CARE at ITER | New project values launched

    Collaboration, Accountability, Respect and Excellence drive the future of fusion for a diverse staff. When Pietro Barabaschi joined as ITER Director-General to [...]

    Read more

Of Interest

See archived entries

Assembly Hall

An ever-changing landscape

The view from the gangway, 55 metres above the floor of the Assembly Hall, is an ever-changing landscape. The 6,000-square-metre staging area accommodates only two permanent features: the twin sector sub-assembly tools (SSAT1 and SSAT2) designed to assemble the massive vacuum vessel sectors, toroidal field coils and thermal shield segments into sector modules. All around them, the movement of workers, elevated platforms, forklifts, rigging elements and giant components composes a slow-motion spectacle—half mechanical ballet, half construction game.

Close to 100 metres from door to wall: the Assembly Hall povides a 6,000-square-metre shop floor to receive, equip and pre-assemble the massive components required for the ITER machine. (Click to view larger version...)
Close to 100 metres from door to wall: the Assembly Hall povides a 6,000-square-metre shop floor to receive, equip and pre-assemble the massive components required for the ITER machine.
The latest arrival (1) in this view taken on 8 April 2022 is vacuum vessel sector #8, manufactured in Korea and delivered to ITER on 1 April. Like a fossilized alien life form, the component has shed its protective cocoon (2), which now stands empty at the lower left of the image.

Close to the newly arrived sector, a toroidal field coil (#9 from Europe), lies in the upending tool (3). Soon, the tool will be moved to its vertical orientation and the magnet coil will be transferred to SSAT1 to be assembled with the second vacuum vessel sector, which has already been equipped with a thermal shield segment (4). A few metres away, SSAT2 holds a close-to-finalized sector module (5), scheduled to be installed in the assembly pit (6) in the coming weeks.

To the right of the twin assembly tools, an area (7) is dedicated to the assembly of the US-procured central solenoid modules.  Of the three cylindrical elements, the greenish one is the first module, delivered to ITER in September 2021. The yellow tool to the left is the lifting fixture that will used to move the modules to the assembly platform (grey) and stack them one atop the other in order to form the 18-metre tall, 1,000-tonne central solenoid.

The structure along the wall, on the right side of the Hall (8) is part of the support system for the waveguides that will connect the gyrotron sources in the Radio Frequency Building to the tokamak machine.

As these lines are being written, the scene in the Assembly Hall has already been transformed, with the house-like cocoon for vacuum vessel sector #8 moved to temporary storage and readied for dismantlement. 

 