Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Inside the pit | From dizzying volume to cramped environment

    There was a time when the assembly pit felt like a huge arena, with toy-like tools scattered on the floor and workers reduced to Playmobil-size figures. Progres [...]

    Read more

  • Fusion world | UKAEA's CHIMERA set to transform fusion component testing

    Construction of a unique testing machine for fusion components is underway at the UK Atomic Energy Authority (UKAEA).  The machine, known as CHIMERA (or Co [...]

    Read more

  • Award | A 30-year friendship with China

    Some thirty years ago, HT-7, China's first superconducting tokamak, was entering operation and experiencing some issues with its ion cyclotron resonance (ICRH) [...]

    Read more

  • Tokamak assembly | Building the feeders, segment by segment

    Through an opening in the Tritium Building just large enough to admit the 11-metre-long components, two magnet feeder segments were introduced this month into t [...]

    Read more

  • Fusion world | Highest French distinction for former ITER Director-General

    Established in 1802 by Napoléon Bonaparte, then the First Consul of the young French Republic, the French Legion of Honour (Légion d'honneur) is the highest of [...]

    Read more

Of Interest

See archived entries

ITER is coming out of the ground

The concrete columns of the 250-metre-long Poloidal Field Coils Winding Facility are all up. Photo: F4E (Click to view larger version...)
The concrete columns of the 250-metre-long Poloidal Field Coils Winding Facility are all up. Photo: F4E
The work on the ITER platform is progressing rapidly. The future Headquarters building is coming out of the ground, the basement is half there and its ceiling is taking shape too. The works are thus well on schedule and should be terminated in the summer of 2012.

As for Tokamak Complex excavation, the first phase of works is finished and soon the trim blasting to complete the excavation will commence. These works will run into early 2011 and will be followed with the pouring of the first concrete in springtime.

The Tokamak Pit is almost finished; soon the trim blasting to complete the excavation will commence. (Click to view larger version...)
The Tokamak Pit is almost finished; soon the trim blasting to complete the excavation will commence.
The construction of the Poloidal Field Coils Winding Facility is also making impressive progress. Most of the floor slab is completed and the concrete columns are up. The crane runway beams are also well underway. The next step now is the mounting of the steel superstructure which will finish the main structural aspects of the building. Here, too, we are on schedule for completion of the final building at the end of 2011.

Early next year, Fusion for Energy, the ITER's European entity, will start with the preparatory works for contractor area II below the Visitors Centre and some parts of the deeper buried networks.

Special thanks to Timothy Watson, Head of the Directorate for the Buildings & Site Infrastructure, for his contribution.


return to the latest published articles