Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Remembering Bernard Bigot, ITER Director-General 2015-2022

    On the ITER site, the machinery of construction was humming just like on any weekday. Workers were concentrating on their tasks, laying rebar for new buildings [...]

    Read more

  • Tokamak assembly | Preparing for the Big Lift

    The distance was short but the challenge daunting: on Thursday last week, the first section of the plasma chamber was lifted 50 centimetres above its suppor [...]

    Read more

  • Image of the week | 13th toroidal field coil arrives from Europe

    The toroidal field coil procurement effort has been one of the longest of the ITER program, initiated by Procurement Arrangements signed in 2007 and 2008. Manuf [...]

    Read more

  • Diagnostics | Final Procurement Arrangement signed

    ITER Diagnostics reached an important milestone in December 2021 when it concluded the last Procurement Arrangement of the diagnostics program. After signing a [...]

    Read more

  • On site | A quick visit to the Control Building

    Work is progressing on the ITER Control Building, ergonomically designed for the 60 to 80 operators, engineers and researchers who will call it home.  [...]

    Read more

Of Interest

See archived entries

ITER is coming out of the ground

The concrete columns of the 250-metre-long Poloidal Field Coils Winding Facility are all up. Photo: F4E (Click to view larger version...)
The concrete columns of the 250-metre-long Poloidal Field Coils Winding Facility are all up. Photo: F4E
The work on the ITER platform is progressing rapidly. The future Headquarters building is coming out of the ground, the basement is half there and its ceiling is taking shape too. The works are thus well on schedule and should be terminated in the summer of 2012.

As for Tokamak Complex excavation, the first phase of works is finished and soon the trim blasting to complete the excavation will commence. These works will run into early 2011 and will be followed with the pouring of the first concrete in springtime.

The Tokamak Pit is almost finished; soon the trim blasting to complete the excavation will commence. (Click to view larger version...)
The Tokamak Pit is almost finished; soon the trim blasting to complete the excavation will commence.
The construction of the Poloidal Field Coils Winding Facility is also making impressive progress. Most of the floor slab is completed and the concrete columns are up. The crane runway beams are also well underway. The next step now is the mounting of the steel superstructure which will finish the main structural aspects of the building. Here, too, we are on schedule for completion of the final building at the end of 2011.

Early next year, Fusion for Energy, the ITER's European entity, will start with the preparatory works for contractor area II below the Visitors Centre and some parts of the deeper buried networks.

Special thanks to Timothy Watson, Head of the Directorate for the Buildings & Site Infrastructure, for his contribution.


return to the latest published articles