Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Making remote handling less remote

    Over a wet and windy three-day period on the ITER site in November, around 90 representatives of the ITER Organization, the Domestic Agencies of Europe and Japa [...]

    Read more

  • The framework for sharing ITER intellectual property

    In signing the ITER Agreement in 2006, the seven ITER Members were agreeing not only to share in the costs of constructing and operating the ITER facility, but [...]

    Read more

  • Wendelstein achieves ultra-precise magnetic topology

    A recent article in the online journal Nature Communications confirms that the complex topology of the magnetic field of Wendelstein 7-X—the world's largest ste [...]

    Read more

  • The Matrix, rigid and fluid

    A fast-growing array of structures and buildings has been emerging across the ITER worksite platform under the control and supervision of the European Domestic [...]

    Read more

  • By road, river and sea

    They travelled by road from the Air Liquide factory near Grenoble, sailed down the Rhône River from Lyon and entered the Mediterranean to the east of Fos-sur-Me [...]

    Read more

Of Interest

See archived articles

ITER is coming out of the ground

-Sabina Griffith

The concrete columns of the 250-metre-long PF Coil Winding Facility are all up. Photo: F4E (Click to view larger version...)
The concrete columns of the 250-metre-long PF Coil Winding Facility are all up. Photo: F4E
The work on the ITER platform is progressing rapidly. The future Headquarters building is coming out of the ground, the basement is half there and its ceiling is taking shape too. The works are thus well on schedule and should be terminated in the summer of 2012.

As for the Tokamak excavation, the first phase of works is finished and soon the trim blasting to complete the excavation will commence. These works will run into early 2011 and will be followed with the pouring of the first concrete in springtime.

The Tokamak Pit is almost finished; soon the trim blasting to complete the excavation will commence. (Click to view larger version...)
The Tokamak Pit is almost finished; soon the trim blasting to complete the excavation will commence.
The construction of the Poloidal Field Coils Winding facility is also making impressive progress. Most of the floor slab is completed and the concrete columns are up. The crane runway beams are also well underway. The next step now is the mounting of the steel super-structure which will finish the main structural aspects of the building. Here, too, we are on schedule for completion of the final building at the end of 2011.

Early next year, Fusion for Energy, the European ITER entity, will start with the preparatory works for the Contractor's Area II below the visitor's center and some parts of the deeper buried networks.

Special thanks to Timothy Watson, Head of the Directorate for the Buildings and Site Infrastructure, for his contribution.


return to the latest published articles