Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Diagnostics | Measuring the behaviour of fast ions in the plasma

    A diagnostic probe, called the "lost alpha monitor," is being carefully designed to measure the behaviour of escaping ions. The lost alpha monitor wil [...]

    Read more

  • Fusion fashion | A collision of worlds

    As Gabriela Hearst, the Creative Director of the fashion brand Chloé, is quick to tell you, she is very excited about hydrogen fusion. She had read about ITER a [...]

    Read more

  • Manufacturing | Cold valve boxes for the ITER cryopumps

    Eight sophisticated 'cold valve boxes' will regulate the forced flow of supercritical helium to the eight cryopumps of the ITER vacuum system. European contract [...]

    Read more

  • Fusion world | A helium campaign kicks off at JET

    After achieving record-breaking results on the Joint European Torus during 2021 experiments with the high-performance fuel mix of deuterium and tritium, EUROfus [...]

    Read more

  • Coil winding table | Seven years of faithful service

    In November 2015, workers from the European contractor Sea Alp Engineering, an Italian company based in Turin, began installing a large circular structure at th [...]

    Read more

Of Interest

See archived entries

ITER is coming out of the ground

The concrete columns of the 250-metre-long Poloidal Field Coils Winding Facility are all up. Photo: F4E (Click to view larger version...)
The concrete columns of the 250-metre-long Poloidal Field Coils Winding Facility are all up. Photo: F4E
The work on the ITER platform is progressing rapidly. The future Headquarters building is coming out of the ground, the basement is half there and its ceiling is taking shape too. The works are thus well on schedule and should be terminated in the summer of 2012.

As for Tokamak Complex excavation, the first phase of works is finished and soon the trim blasting to complete the excavation will commence. These works will run into early 2011 and will be followed with the pouring of the first concrete in springtime.

The Tokamak Pit is almost finished; soon the trim blasting to complete the excavation will commence. (Click to view larger version...)
The Tokamak Pit is almost finished; soon the trim blasting to complete the excavation will commence.
The construction of the Poloidal Field Coils Winding Facility is also making impressive progress. Most of the floor slab is completed and the concrete columns are up. The crane runway beams are also well underway. The next step now is the mounting of the steel superstructure which will finish the main structural aspects of the building. Here, too, we are on schedule for completion of the final building at the end of 2011.

Early next year, Fusion for Energy, the ITER's European entity, will start with the preparatory works for contractor area II below the Visitors Centre and some parts of the deeper buried networks.

Special thanks to Timothy Watson, Head of the Directorate for the Buildings & Site Infrastructure, for his contribution.


return to the latest published articles