We can all look back on 2011 with a great deal of satisfaction. After a long period of anticipation and the beginning of construction in 2010, the pace of works accelerated during the last twelve months and the ITER landscape has now been completely transfigured.
The civil works, exterior cladding, interior fittings and road works for the Poloidal Field Coils Winding Facility were all completed during the year on time and on budget. This is a positive, encouraging signal to my European Domestic Agency (F4E) colleagues in Barcelona and for the project as a whole. Throughout the 18-month project we enjoyed excellent relations with our contractors, the French consortium Spie Batignolles/Omega Concept/Setec, and works were carried out in good spirit. During the first weeks of January, this facility will be handed over to F4E by the contractors.
Spectacular progress was also made in the Tokamak Pit. It's only the beginning, of course, but the large-scale excavation and foundation works that have occupied hundreds of workers signify the real start of ITER. Works have progressed on schedule, despite some very rainy periods, and I'm very thankful to be able to report that we have had no major incident or accident—quite a good record for such a large and complex construction area.
Safety remains a priority for the entire F4E team. We have taken the time to provide clear guidelines on safety and to make sure that these guidelines were well understood through training. As a nuclear facility, the works in the Tokamak Pit also undergo regular inspection. Both internal audits and those conducted by the French nuclear safety regulators (ASN) have confirmed the good quality of the works.