Lettres d'information

Choisissez ce que vous souhaitez recevoir :

Merci de renseigner votre adresse de messagerie électronique :

@

Votre adresse email ne sera utilisée que dans le cadre de campagnes d'information ITER Organization auxquelles vous êtes abonné. ITER Organization ne communiquera jamais votre adresse email et autres informations personnelles à quiconque ou dans le cadre d'informations commerciales.

Si vous changez d'avis, il vous est possible de vous désinscrire en cliquant sur le lien 'unsubscribe' visible dans vos emails provenant d'ITER Organization.

Pour plus d'information, veuillez consulter notre Politique de confidentialité.

Actu & Médias


Pour les actualités en français, voir la page Actus & Médias.

Laying tracks for the elevated railway

They're as thick and strong as railroad tracks and could easily carry the equivalent of four TGVs, two Eurostars or 15 steam locomotives. The steel rails that are being installed 43 metres above the basemat of the Assembly Hall are an essential part of the lifting system that will handle components weighing up to 1,500 tonnes.

43 metres above the basemat of the Assembly Hall, workers are laying the rails for the lifting system that will handle components weighing up to 1,500 tonnes. (Click to view larger version...)
43 metres above the basemat of the Assembly Hall, workers are laying the rails for the lifting system that will handle components weighing up to 1,500 tonnes.
When rails are laid on the ground, they rest on a bed of crushed stone (the track ballast) that distributes the load of the passing trains. In the ITER Assembly Hall, the ballast role is played by massive steel elements (9.3 metres long, 20 tonnes) called railway beams.

Resting on the vertical pillars of the Assembly Hall and running the entire length of the building, the railway beams form a perfectly smooth steel track upon which the rails can be affixed.

It will take a few weeks to install the rails and fine tune their alignment. (Click to view larger version...)
It will take a few weeks to install the rails and fine tune their alignment.
On Thursday 12 May, on the north side of the Assembly Hall, the first 18-metre length of rail was lifted, carefully deposited and fastened with heavy clips to the ledge formed by the railway beams. It will take a few weeks to install the rails and fine tune their alignment in time for the installation, beginning next month, of the girders and trolleys of the travelling crane.


return to the latest published articles