Depending on their location, cables need to meet additional requirements. In areas exposed to nuclear radiation for instance, they need to be able to sustain different accidental conditions such as radiation, high temperature and pressures. Cables for use in the vacuum vessel are designed to be compatible with this challenging environment.
The accumulation of such properties can make cable production challenging, says Beltran. "Some cables have an additional anti-rodent protection—their smell drives rats away," he says about cables that will cross
underground tunnels to connect the different buildings on the ITER worksite.
Coordination and sequencing of the individual work phases constitute the biggest challenge according to Beltran—planning not only the order in which buildings need to be wired (many of them in parallel), but also the sequence of installation for structural supports, components and cables inside the buildings. "Accessibility is a big issue when planning cable installations. We need to be sure that cable trays and cables—once put in place—do not pose an obstacle for other installation activities," he explains.
Big deadlines are approaching for wiring activities. By the end of the year, several buildings including the Assembly Building and the Magnet Power Conversion buildings, must be fully equipped with cables and related electrical building services such as HVAC, power sockets, switches and lights. The commissioning of electrical systems will begin in January in the Assembly Building, so that all building services are in full operation when the first vacuum vessel sector arrives from Korea in the middle of next year.
In the meantime, the telltale signs of cable installation—stacks of cable trays and cable drums outside of the Cryoplant Building—pinpoint the upcoming cable installation priorities on the ITER worksite.