Lettres d'information

Choisissez ce que vous souhaitez recevoir :

Merci de renseigner votre adresse de messagerie électronique :

@

Votre adresse email ne sera utilisée que dans le cadre de campagnes d'information ITER Organization auxquelles vous êtes abonné. ITER Organization ne communiquera jamais votre adresse email et autres informations personnelles à quiconque ou dans le cadre d'informations commerciales.

Si vous changez d'avis, il vous est possible de vous désinscrire en cliquant sur le lien 'unsubscribe' visible dans vos emails provenant d'ITER Organization.

Pour plus d'information, veuillez consulter notre Politique de confidentialité.

Actu & Médias


Pour les actualités en français, voir la page Actus & Médias.
Coil manufacturing in Europe

Insertion is a success

The first superconducting winding pack made in Europe for ITER's D-shaped toroidal field coils is now ensconced in its 200-tonne protective case. The first-of-a-kind insertion operation was carried out successfully at SIMIC, in northern Italy.

European contractors perform the first insertion operation of toroidal field coil manufacturing. The completed unit—winding pack plus case—weighs approximately 310 tonnes. © SIMIC (Click to view larger version...)
European contractors perform the first insertion operation of toroidal field coil manufacturing. The completed unit—winding pack plus case—weighs approximately 310 tonnes. © SIMIC
On the insertion rig at SIMIC, the 110-tonne winding pack is laid out flat. On either side, the two halves of the steel coil case—the straight inboard segment and the D-shaped outboard segment—have been positioned at the same height. Working within tolerances of 0.2 mm, the insertion tooling slowly brings the "pieces" together and the winding pack disappears inside the heavy steel case.

This first successful insertion operation is a prelude to nine others to come, as the European Domestic Agency Fusion for Energy is procuring ten toroidal field coils from winding packs manufactured by the ASG consortium (Europe) and structural cases procured by Japan. SIMIC is the European company that has been selected for final cold testing, insertion and welding activities.

Seamlessly: case halves procured by Japan from Hyundai Heavy Industries (Korea) and Mitsubishi Heavy Industries (Japan) closed without incident over the winding pack manufactured in Europe by the ASG consortium. © SIMIC (Click to view larger version...)
Seamlessly: case halves procured by Japan from Hyundai Heavy Industries (Korea) and Mitsubishi Heavy Industries (Japan) closed without incident over the winding pack manufactured in Europe by the ASG consortium. © SIMIC
Under the contract with SIMIC, winding packs shipped from ASG are cold tested at -193 degrees Celsius (80 K) using a combined cycle of nitrogen and helium. Insertion into the steel structural case comes next, in an operation requiring sophisticated laser dimensional control technology and complex tooling in order to move and fit components weighing hundreds of tonnes with millimetre-level precision. Finally the interior cover plates will be attached and welded in compliance with stringent standards. The thickness of the welds (up to 130 mm) and the fact that welding will have to be carried out from one side only adds to the challenge of this final operation.

Welding is expected to take from four to six months, followed by the injection of resin to fill any gaps between the winding pack and the case.