Blasting, comfort, and the colour of champagne!
The Hot Cell Facility will be contiguous to the Tokamak Complex. Its foundations—less profound than those of its immediate neighbour—nonetheless require final blasting to finish the contours before foundation work begins.
The contractor responsible for excavation and foundation works, GTM Construction, is erecting a tower crane at each of the four corners of the Tokamak Complex area prior to concrete pouring works which are scheduled to begin in May and last the rest of the year.
At the peak of construction activity on the platform some 20 of these tower cranes will be in action, spread over the different work sites. The four silos of the on-site concrete batching plant are ready for the continuous ballet of trucks that will soon be seen loading, delivering, returning to wait in line, loading, delivering...
Once completed, the Poloidal Field Coils Winding Facility will be champagne and orange coloured.