Double pancake winding is a highly precise technical operation that has required the development of advanced technologies and processes. The most important technologies for the fabrication of PF1 were developed at the Efremov Institute (JSC "NIIEFA"), which also designed, manufactured and tested a large part of the equipment. From the signing of the
Procurement Arrangement with the ITER Organization in 2011, through the fabrication of poloidal field
conductor and the latest milestone—winding completion—development and manufacturing activities have required eight years to date.
Coil manufacture is underway at the Sredne-Nevsky Shipyard near Saint Petersburg, where the finalized coil assembly will leave the plant directly atop a barge for the nearby Neva River. (
See more on the Shipyard's barge/assembly platform here.) The completed coil is expected early in 2021.