Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • In-vessel electrical systems | What it takes to wire up a fusion reactor

    While the challenges of keeping cables operational in harsh environments such as jet engines and nuclear fission reactors have been understood for a long time, [...]

    Read more

  • Assembly preparation | Off goes the lid

    In the summer of 2017, a circular platform was installed inside of the large steel-and-concrete cylinder of the Tokamak pit. The 200-tonne structure was meant t [...]

    Read more

  • Deliveries | Two coils on their way

    For the past five years, 'highly exceptional loads' (HEL) have been successfully travelling along the ITER Itinerary to be delivered to the ITER site. As the pr [...]

    Read more

  • ITER NOW video | Ready for the big lifts

    This new video in our "ITER NOW" series provides an insider's view of the recent load tests performed as the ITER Organization prepares for the machin [...]

    Read more

  • Divertor | Far more than a fancy ashtray

    It has been likened to the filter of a swimming pool or an oversized ashtray. It has been called alien in shape and hellish in its affinity for heat. But whatev [...]

    Read more

Of Interest

See archived entries

Big crane has a sibling

The massive 1,500-ton double overhead bridge crane that was installed in the Assembly Hall in June now has a sibling. Just as long and as impressive, albeit much lighter, the girders for the 50-tonne auxiliary crane were lifted last week onto their rails at a height of 39 metres.

This time, the weight of the auxiliary crane girders and the installation height made it possible to use a telescopic crane that operated from inside the Assembly Hall.<br /><br /> (Click to view larger version...)
This time, the weight of the auxiliary crane girders and the installation height made it possible to use a telescopic crane that operated from inside the Assembly Hall.

The operation last June had required the use of one of the tallest and most powerful crawler cranes available. Operating from outside the building, it lifted the girders through an opening in the building's roof.

This time, the weight of the auxiliary crane girders (42 tonnes as compared to 186) and the installation height (39 metres as compared to 42) made it possible to use a telescopic crane that operated from inside the Assembly Hall.

The full lifting system for the pre-assembly of Tokamak components is now in place. When the Tokamak Building is complete, the rails for both the principal and auxiliary cranes will be extended 80 metres to allow for the transport of components between the Assembly Hall and the Tokamak assembly area.


return to the latest published articles