Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryostat thermal shield | A "strong back" for a fragile component

    The lower cylinder thermal shield is a large silver-plated component, circular in shape and five metres tall, which fits inside the depression in the cryostat b [...]

    Read more

  • Diagnostic shielding | B4C ceramic bricks prove their worth

    A number of materials can effectively shield diagnostic equipment from the neutron flux coming from the plasma. To find the best one, the diagnostics team at IT [...]

    Read more

  • Image of the week | The cryostat top lid, batch after batch

    Batch after batch, the elements for the top lid of the ITER cryostat keep arriving from India. As of today, 7 out of the 12 required segments have been delivere [...]

    Read more

  • Cooling water system | The tanks within a tank

    Deep inside the bowels of the Tokamak Building, the entrance to one of most spectacular rooms of the whole installation resembles that of a broom cupboard. [...]

    Read more

  • ITER assembly | Last major assembly contract signed

    One year after finalizing two major machine assembly contracts, the ITER Organization has chosen the contractors who will carry out assembly and installation ac [...]

    Read more

Of Interest

See archived entries

The crown

Unique but inspired by history

On the floor of the vast amphitheatre that will accommodate the ITER machine, one of the most complex and most strategic structures of the Tokamak Building is taking shape.

Down on the floor of the Tokamak Pit the steel reinforcement for about one-fourth of the crown has been set into place and—thanks partly to a recently-implemented night shift—work is progressing quickly on the remaining three-fourths. (Click to view larger version...)
Down on the floor of the Tokamak Pit the steel reinforcement for about one-fourth of the crown has been set into place and—thanks partly to a recently-implemented night shift—work is progressing quickly on the remaining three-fourths.
Reminiscent of a spiked crown—not unlike the one atop the Statue of Liberty—the structure is designed to support the combined mass of the cryostat and Tokamak (25,000 tonnes) while transferring the forces and stresses generated during plasma operations to the ground.

Aptly enough, the structure sitting at the bottom of the Tokamak Pit is called ... a "crown."

Its principle is inspired by the "flying buttress"—an architectural solution that was implemented eight centuries ago to prevent a cathedral's walls from collapsing outward under the weight of its stone ceiling and slate roof.

In the long story of the design of the ITER buildings, the crown is a relative newcomer: up until 2012, the baseline solution to support the machine consisted of a circular arrangement of 18 sturdy steel columns.

However as models and simulations were refined, it became clear that the load transfer from the Tokamak's mass and movements to the floor of the Tokamak Complex (the B2 slab) was not totally satisfying.

Machine "up lift" from a potential vertical displacement event,  cryostat "shrinkage" from a possible ingress¹ cooling event  ... these potential events were of particular concern to safety experts.

Developing an alternate option to the columns led to a one-year collaborative effort involving several ITER departments, the European Domestic Agency responsible for building construction, and their architect engineer Engage.


Inspired by history but unique to ITER, the radial walls are the ''spikes'' of the crown that will support the combined mass of the cryostat and Tokamak (25,000 tonnes) while transferring the forces and stresses generated during plasma operations to the ground. (Click to view larger version...)
Inspired by history but unique to ITER, the radial walls are the ''spikes'' of the crown that will support the combined mass of the cryostat and Tokamak (25,000 tonnes) while transferring the forces and stresses generated during plasma operations to the ground.
Engage eventually suggested mobilizing the resistance capacity of the bioshield wall (3.2 metres thick at its base) and using it as an abutment for a set of 18 deeply imbedded radial walls—the "flying buttress" solution.

The full constructability of this innovative structure, both inspired by history and unique to ITER, needed to be demonstrated however. In October 2017, a full-scale mockup, three metres high, was erected on the ITER platform to answer the questions that even the most detailed 3D models couldn't.

Six months have passed. Down on the floor of the Tokamak Pit the steel reinforcement for about one-fourth of the crown has been set into place and—thanks partly to a recently-implemented night shift—work is progressing quickly on the remaining three-fourths.

Massive steel transition pieces, 3.5 tonnes each, have been placed atop every radial wall to optimize the transfer of loads to the ground. Lengths of thin red plastic piping are being inserted into the steel rebar to circulate cooling water during the concrete pouring phase; two kilometres of this piping will be required in all for the crown. Finally, workers are busy welding a thin "fire mesh" to the outer face of the walls to within millimetric tolerances. (See gallery below for details.)

"Everything we are implementing now has been tested and validated on the mockup: the rebar installation sequence, the concrete formulation and pouring procedures, the temperature monitoring, the cooling system arrangement and sequences ..." explains Armand Gjoklaj of the ITER Building & Civil Works Section.

And the mockup's mission is not over yet—the installation procedure for high-strength "top plates" still needs to be tested and validated. These 3.5-tonne elements will sit on top of the steel transition pieces to receive 18 semi-spherical "bearings."

The first concrete pour for the crown is scheduled in mid-May and the entire structure should be finalized by September. And as all surfaces of the nuclear buildings need to be clean and decontaminable, a huge paint job will follow on the bioshield inner walls, on the crown's radial walls and on the floor.

The concrete amphitheatre of today will turn into a polished jewel box, ready to accommodate one of the most extraordinary creations of the human mind: the ITER Tokamak. 

¹The liquid helium cooling circuits for the superconducting magnets pass through the cryostat. In case of a breach, the sudden drop in temperature would cause a "shrinking" of the cryostat.


return to the latest published articles