Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Port cells | All 46 doors in place

    In ITER, ordinary objects and features often take on an awesome dimension. Take the doors that seal off the port cells around the Tokamak for instance. Doors th [...]

    Read more

  • Toroidal field coils | Two make a pair

    One of the essential 'building blocks' of the ITER Tokamak is the pre-assembly of two toroidal field coils, one vacuum vessel sector and corresponding panels of [...]

    Read more

  • Industrial milestone | Cryostat manufacturing comes to an end in India

    With a flag-off ceremony on 30 June, India's L&T Heavy Engineering marked the end of an eight-year industrial adventure—the manufacturing of the ITER cryost [...]

    Read more

  • Local partners | A celebration for ITER's "vital artery"

    ITER is made possible through the work of thousands of scientists, engineers, workers of all trades and industries across the globe. It is also made possible by [...]

    Read more

  • Photo reportage | Travelling with a coil

    From the salt marshes of the inland sea Étang-de-Berre to the rolling hills around the ITER site (with a view of some of the highest alpine summits) an ITER con [...]

    Read more

Of Interest

See archived entries

Tokamak Pit

Big steel elbow in place

A cryostat feedthrough delivered by the Chinese Domestic Agency has become the first metal component of the machine to be installed in the Tokamak Pit, in an operation orchestrated over two weeks by the ITER Organization.

Into the slim opening of the cryostat crown: a break in the concrete had been left by building contractors for the installation of the cryostat feedthrough for poloidal field coil #4. The operation was successfully carried out on 6 December. (Click to view larger version...)
Into the slim opening of the cryostat crown: a break in the concrete had been left by building contractors for the installation of the cryostat feedthrough for poloidal field coil #4. The operation was successfully carried out on 6 December.
An activity that began with the transfer of the component to the vicinity of the Tokamak Complex—and that was pursued as the 10-metre, 6.6-tonne component was introduced into the Pit through an opening in the bioshield roof—has now been concluded through the final positioning of the feeder segment in the building.

In the final lift sequence, the elbow-shaped component was raised by the monorail crane at the bottom of the Tokamak Pit, rotated above the cryostat crown, and lowered into a slim opening that had been left in the concrete circle in anticipation of this very installation sequence. Positioned on a temporary support tool supplied by the Korean Domestic Agency, technicians used cables to draw the horizontal segment of the feedthrough into the bioshield opening, while the vertical segment fell into place between the crown and the bioshield. (See more detail in the photo gallery below.)

Final adjustments were performed through metrology measurements to fall within +/- 2 mm with respect to the Tokamak Global Coordinate System.

If magnet feeders are the essential lifelines of the ITER magnets—carrying electricity, cryogenic fluids and instrumentation cables—"feedthroughs" are the part of the feeder assemblies that cross through the bioshield and the cryostat. This first completed unit had been delivered last year to the Magnet Infrastructure Facilities for ITER (MIFI) where, as a first-of-a-kind component, it underwent high-voltage tests, leak tests and endoscopic inspection.

Ultimately, the feedthrough will be joined by two other components—an in-cryostat feeder (nearest the vacuum vessel) and a coil termination box (outside the bioshield)—to connect to poloidal field coil #4, one of the two largest of the machine's six poloidal field coils (24 metres in diameter).

"A large number of actors played a critical role in the installation operation that concluded last week," notes Bruno Levesy, Group Leader of the In-Cryostat Assembly Section, with satisfaction, "The Domestic Agencies of China (fabrication) and Korea (tooling), the ITER Organization logistics provider DAHER (transport), European Domestic Agency building contractors, ITER's Construction Management-as-Agent contractor, and the French company CNIM (which won the early works contract in the Tokamak Pit) all participated." Giobatta Lanfranco (Construction Team) and Bruno were the most involved staff members of the ITER Organization. "It has been a good practice in coordination for the many activities to come."


return to the latest published articles