Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Tokamak Complex | A changing landscape

    For the past three years, the view from the top of the highest worksite crane has not changed much. Inside of the Tokamak Complex, 80 metres below, concrete gal [...]

    Read more

  • Ion cyclotron heating | How to pump 20 MW of power into 1 gram of plasma

    To power the ion cyclotron system, the ITER Organization and its partners are designing not only new antennas, which will be housed in the tokamak vessel, but a [...]

    Read more

  • 10 years ago in Newsline | White, silent and immobile

    Ten years ago, in mid-January 2010, heavy snow fell on Provence and the white blanket that settled on the ITER platform accentuated its main feature: utter empt [...]

    Read more

Of Interest

See archived entries

Sub-assembly tools

A 12-tonne beam, a crane and a little push

There is nothing remarkable about lifting a 12-tonne beam. Except when it happens in the spectacular setting of the ITER Assembly Hall, and the beam needs to be fitted with extreme precision into a structure as monumental as the ITER sector sub-assembly tools.

The first 12-tonne beam is slowly lifted 22 metres above ground. (Click to view larger version...)
The first 12-tonne beam is slowly lifted 22 metres above ground.
Towering 22 metres above ground, the vacuum vessel sector sub-assembly tools (SSATs) are formidable handling machines that will be used to pre-assemble vacuum vessel sectors with a pair of toroidal field coils and thermal shield segments before integration in the machine.

The assembly of SSAT-1 began in November 2017 and is now complete. Work on its identical twin SSAT-2 started in September the following year and is now entering its final phase.

Positioned on both sides of the beam, CNIM specialists precisely align the suspended beam and the massive supporting pillars—an operation that can only be performed manually. (Click to view larger version...)
Positioned on both sides of the beam, CNIM specialists precisely align the suspended beam and the massive supporting pillars—an operation that can only be performed manually.
Part of Korea's contribution to ITER, the tools are assembled by French contractor CNIM. Lessons learned from SSAT-1 have reduced assembly time for SSAT-2 by approximately one-third.

On Wednesday 9 January, installation operations began for some of the last elements: two 12-tonne beams that stabilize the massive pillars of the machine.

Click here to watch a video of the installation.



return to the latest published articles