Poloidal field coil #6 | The home stretch

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Augmented reality | Assessing the future work environment

    As part of their collaboration within the Site Support Agreement*, ITER and its neighbour CEA are developing a novel approach to explore, analyze and assess the [...]

    Read more

  • Diagnostics and instrumentation | First welding on the vacuum vessel

    Beginning in 2035, ITER will open a window into "burning plasmas"—a state of matter that exists in the core of stars only. Observing, assessing and mo [...]

    Read more

  • Assembly | Machining workshop opens on site

    Construction of an on-site machining workshop began in December 2019 and was completed on schedule in September 2020.The new workshop will be operated by the D [...]

    Read more

  • Neutral Beam Test Facility | Power is ready for the prototype injector

    The European Domestic Agency has carried out successful site acceptance tests at the ITER Neutral Beam Test Facility on power supply equipment installed ov [...]

    Read more

  • In-vessel coils | First components arrive on site

    ITER has received the first shipments of mineral-insulated conductor for ITER's in-vessel coils. The first lengths are destined for winding and bending trials a [...]

    Read more

Of Interest

See archived entries

Poloidal field coil #6

The home stretch

In Hefei, China, a 400-tonne ring magnet procured by the European Domestic Agency is entering the final phase of production—resin impregnation. In just over one month, the component will be ready for packing and shipment to the ITER site.
This mould in nearly ready to receive poloidal field coil number #6 for vacuum pressure impregnation, a process that takes two to three weeks (including leak testing and drying). (Click to view larger version...)
This mould in nearly ready to receive poloidal field coil number #6 for vacuum pressure impregnation, a process that takes two to three weeks (including leak testing and drying).
Six years after a collaboration agreement was signed between the European Domestic Agency Fusion for Energy, responsible for procuring the component, and supplier ASIPP (the Institute of Plasma Physics/Chinese Academy of Sciences), ITER's sixth poloidal field coil, PF6, is being prepped for final coil impregnation.

PF6 is the second smallest of the ITER ring magnets in terms of diameter (10 metres), but the heaviest due to a higher number of stacked pancakes (nine instead of six or eight), a greater number of coil turns (twice as many as PF1) and exceptionally heavy clamps.

This last major production step ensures that the complete stack of nine double pancakes is electrically insulated and creates a rigid assembly. Following vacuum pressure impregnation and the completion of piping and instrumentation, the coil will be tested and packed for shipment.

Some of the external components of the coil—joint and clamps—are wrapped by ASIPP technicians before vacuum pressure impregnation. (Click to view larger version...)
Some of the external components of the coil—joint and clamps—are wrapped by ASIPP technicians before vacuum pressure impregnation.
Fusion for Energy and ASIPP teams have collaborated closely throughout the multiyear fabrication process, from qualification activities back in 2016 and 2017, through pancake winding and pancake impregnation. When it reaches the ITER site, the completed component will be delivered for cold testing to the European Poloidal Field Coils Winding Facility.

In the assembly schedule of the ITER device, PF6 will be the first of the six poloidal field coils to be installed, lowered by overhead crane into the "dish" of the cryostat base to its position under the vacuum vessel.

A ceremony for component completion is planned on 18 July at ASIPP.

Click here to see a report on the Fusion for Energy website.


return to the latest published articles