Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Mag

Of Interest

See archived entries

Vacuum vessel sector #6

On its way

A 440-tonne, 40-degree sector of the ITER vacuum vessel left Busan, Korea, on Sunday 28 June.

Before leaving the Hyundai Heavy Industries factory in Ulsan, Korea, the 440-tonne sector was wrapped and inserted into protective casing. Sector #6 is seen on its side in this photo with one of its two port stub extensions visible. (Click to view larger version...)
Before leaving the Hyundai Heavy Industries factory in Ulsan, Korea, the 440-tonne sector was wrapped and inserted into protective casing. Sector #6 is seen on its side in this photo with one of its two port stub extensions visible.
A unique component has taken to the sea—one that was more than ten years in the making.

As the first of four sectors to be procured by the Korean Domestic Agency, vacuum vessel sector #6 was the first to progress through every pre-manufacturing, manufacturing, and testing phase. The component's complex geometry, a high number of interfacing parts, strict tolerances, and nuclear safety compliance requirements only increased the challenge for the manufacturing team at Hyundai Heavy Industries. As a first-of-a-kind component, it was also important to create a rigorous documentation trail—both to inform the manufacturing of other sectors, and to facilitate the component's integration into the machine once at ITER.

Thanks to lessons learned on sector #6, three other sectors—#7, #8 and #1—are all at an advanced stage of manufacturing in Korea (>75 percent). Five other sectors are in fabrication under the responsibility of the European Domestic Agency.

Vacuum vessel sector #6 is loaded on board the ''REGINE'' on 26 June. Shipment to France should take just under one month. (Click to view larger version...)
Vacuum vessel sector #6 is loaded on board the ''REGINE'' on 26 June. Shipment to France should take just under one month.
When it arrives at ITER later this summer, sector #6 will be brought into the Assembly Building and transferred by overhead crane to a laydown area. After a final helium leak test and site acceptance test, the component will be ready for handover to the ITER Organization assembly contractor responsible for the vessel (TAC2) for a number of initial activities such as the installation of diagnostics, instrumentation and cable trays.

From there, the component will be transferred to the sector sub-assembly tool for assembly with toroidal field coils #12 and #13, and sector-specific vacuum vessel thermal shields.



return to the latest published articles