Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Fusion world | Public/private consortium is building the DTT tokamak

    The Divertor Test Tokamak in Italy is creating a new model for engagement with industry in fusion research. ITER helped to pave the way. The Divertor Test Tokam [...]

    Read more

  • Image of the week | An architectural paradox

    There is something deliberately paradoxical in the architectural treatment of the ITER buildings. On the one hand, the alternation between the mirror-like stai [...]

    Read more

  • Former French Prime Minister | A fan then and now

    For Jean-Pierre Raffarin, former Prime Minister of France (2002-2005) who visited ITER on Friday 15 March, touring the ITER installation with ITER Director-Gene [...]

    Read more

  • CARE at ITER | New project values launched

    Collaboration, Accountability, Respect and Excellence drive the future of fusion for a diverse staff. When Pietro Barabaschi joined as ITER Director-General to [...]

    Read more

  • Blanket | Midway through shield block procurement

    It all begins with a forged stainless-steel block weighing nine tonnes. As machining and deep-drilling operations commence, the rectangular block progressively [...]

    Read more

Of Interest

See archived entries

Coil winding table

Seven years of faithful service

In November 2015, workers from the European contractor Sea Alp Engineering, an Italian company based in Turin, began installing a large circular structure at the south end of the on-site Poloidal Field Coil Winding Facility. As weeks and months passed, more tooling was added, with functions that were quite inscrutable for the non-specialists: sturdy tower-like devices, what looked like a giant tape dispenser, walkways, gantries, steel cylinders and electrical cubicles. All in all, some 350 tonnes of equipment for Europe's "coil winding station."

Dismantled during the month of August, the winding station's tooling and machinery are now waiting to be moved out of the building and, possibly, to start a new life in a new environment. (Click to view larger version...)
Dismantled during the month of August, the winding station's tooling and machinery are now waiting to be moved out of the building and, possibly, to start a new life in a new environment.
For the past seven years, this unique combination of tooling and machinery has fulfilled its mission—turning more than 50 kilometres of jacketed niobium-titanium cable delivered by China into 30 production "double pancakes" required by the four large ring-shaped poloidal field coils manufactured on site by Europe.

During winding phase of production, spooled conductor was uncoiled and straightened before it passed through cleaning and sandblasting to prepare its surface for several layers of glass-fibre insulating tape. Then, as the winding table rotated slowly, the conductor was wound into double-layer pancakes in the precise dimensions required for the coil in question—either 17 or 24 metres in diameter. These double pancakes then moved down the line to the other production stations of the coil winding facility.

Here's how the winding table looked in July, right before it was dismantled. The on-site manufacturing of the four largest ITER poloidal field coils is the result of expertise from 14 different companies or entities. Over the past seven years, more than 300 engineers, technicians and operators have contributed to this unique industrial adventure. (Click to view larger version...)
Here's how the winding table looked in July, right before it was dismantled. The on-site manufacturing of the four largest ITER poloidal field coils is the result of expertise from 14 different companies or entities. Over the past seven years, more than 300 engineers, technicians and operators have contributed to this unique industrial adventure.
Today, two finalized coils (PF5 and PF2) have left the facility, and two others (PF3 and PF4) are in the final stages of fabrication at the far end of the building. The winding station is needed no more.

LESSONS LEARNED

In the complex step-by-step process of coil manufacturing, the winding table was just the opening act. Once wound, double pancakes were resin impregnated individually, then stacked and connected (each coil comprises 6 to 8 double pancakes), resin impregnated again as a complete assembly, and finally cold-tested before being prepared for installation or storage. The first coil (PF5) took four years to fabricate (2017-2021). For its sibling PF2 experience acquired and lessons learned, both technical and organizational, reduced the process by more than 12 months.

Dismantling operations began early August and lasted throughout the month. Where the table and its machinery once stood, individual components are now waiting to be moved out of the building and, possibly, to start a new life in a new environment. On 28 July 2022 the Official Journal of European Union posted a "prior information notice" for the sale of these highly valuable assets. In the vast clean space that has been cleared, the ITER Organization will be installing a new kind of station: three port plug test stands to put the steel plugs that will seal off each tokamak port opening to the test before their installation in the machine.

The disposal of the winding installation and the reassignment of the space it occupied does not signify the end of coil production activity in the facility. The two largest coils (24 metres in diameter) are still in production, with expected completion dates of mid-2023 (PF4) and mid-2024 (PF3) respectively.

Beginning in 2012 with the delivery of the 13,000-square-metre production facility, the making of ITER's four largest poloidal field coils has brought together hundreds of specialists from more than a dozen European contractors.

Beyond the challenges of manufacturing components of a size and complexity never achieved before, the success of this formidable industrial adventure has rested on the close coordination of contractors and a sharp learning curve that considerably reduced manufacturing time over the years (see box).



return to the latest published articles