Tokamak Building
Full steam ahead
In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving scaffolding and formwork in preparation for the next day's tasks. Responsible for civil engineering and construction, the European Domestic Agency is working to meet an important date on the ITER calendar—March 2020, when the first limited crane access between the Assembly Hall and the Tokamak Building is needed for major installation activities. In the months ahead there will be increased co-activity in the area, as building teams continue to execute civil works contracts (2,000 people currently) at the same time as ITER Organization contractors begin on installation activities. The ITER Organization is preparing now to tender the principal contracts related to assembly and installation works.