Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Machine assembly

Stay tuned for a remarkable lift

Inside the ITER assembly theatre, a major lift event is imminent. This 3D animation takes us through the steps that will be necessary to transport the first 1,200-tonne section of the vacuum vessel into the Tokamak pit.

Click to view the video...


Vacuum vessel sector #6 will always have a special place in the ITER story. Of the nine sectors that will form the torus-shaped plasma chamber, it was the first to be received (in August 2020), the first to get fitted with instrumentation, the first to be upended to vertical, and the first to be docked in a standing sector sub-assembly tool.

The 440-tonne double-walled steel sector manufactured by Hyundai Heavy Industries and supplied by the Korean Domestic Agency for ITER spent just about one year in vertical tooling, as elements were added to create the first complete "sub-assembly" of the vacuum vessel. A complete set of vacuum vessel thermal shielding plus two toroidal field magnet coils were positioned with the highest degree of accuracy and adjusted with precision by the actuators of the tool.

Lessons learned with these first-of-a-kind operations have already facilitated work on subsequent sectors.

Now, the ITER Organization construction teams, including the TAC-2 assembly contractor DYNAMIC, are preparing for the crowning event in the sequence—the transfer by overhead crane of the 1,250-tonne, 40° section from tooling into the Tokamak assembly pit.

The final preparatory rigging activities are underway.

Because the 40° section must be lifted over the rim of the bioshield on its way to the pit—and because the large mass to be lifted necessitates the use of a rigging attachment called the "dual crane heavy lifting beam" that adds to the height of the ensemble—the lift will be one of the tallest assemblies to be handled by the overhead crane system.

In the 3D animation above, you can see how the different rigging elements combine to carry out the necessary steps, from extraction from the tool, to rotation, transfer, and descent.

-          The dual crane heavy lifting beam (in yellow) allows the cranes to work in tandem and facilitates the rotation of the sub-assembly from its tooling orientation to the orientation required for installation in the pit.

-          The sector lifting tool (in grey, directly underneath) connects directly to the beam supporting the sub-assembly, and has a balancing control system to precisely position the load's centre of gravity.

-          The radial beam that supports the assembly directly, and which played a role in docking the vacuum vessel sector in tooling, is designed to continue to support the sub-assembly during in-pit sector-to-sector welding by bracing itself between the tall centre column in the pit and brackets on the surrounding wall.

This long-planned operation is imminent. At the centre of the first-completed sub-assembly of the ITER vacuum vessel, sector #6 will once again be a trailblazer.

The animation is also on the ITER Organization's YouTube page (courtesy of Brigantium Engineering).




return to the latest published articles